Extensions of time Flashcards Preview

Building Surveying > Extensions of time > Flashcards

Flashcards in Extensions of time Deck (8)
Loading flashcards...
1

What clause is extensions of time dealt with?

2.20 Relevant events

2

What is a relevant event?

Variations

CAI

Deferment of possession

3

When must contractor give notice?

When it becomes reasonably apparent

4

When have you experienced a delay?

On Ldubs for the plant deck remediations?

5

How did you assess the plant deck delay was appropriate for an extension of time?

The contractor provided a delay notice

I then undertook a 'Critical Path Analysis'.

6

What method did you use for the delay analysis and are there alternatives?

Critical Path

There is also
-Overview of facts
-Comparing actual and planned progress

7

How did you undertake the critical path analysis?

I analysed the works which were critical to completion using Microsoft Project.

The logic link between the the new plant deck and the reinstatement/replacement of plant was estimated two months and an additional month was included due to the consultant work required.

8

What are the advantageous of using the critical path analysis?

Using software (Micro Project) allowed dynamic reactions on impact of delay. For instance, I can enter extensions of time onto critical pathways quickly and accurately.