Q

A project is a well defined initiative, it have a specific goal and a specific scope (time frame)

A

For example : Improve road conditions is not a project it is a goal.
The goal is not a project it contains several projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Most project get delayed and budget overrun

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Comparison of construction industry with manufacturing industry

A

Manufacturing industry (like planes books…)
Similarities : time frame , design planning bidding manufacturing).
BOth are product driven industries.
Differences:
Manufacturing industries deliveres identical product (mass production system) whereas construction industries delivers unique products.

Ownership: In construction industry the owner gets the process started (AUB for example). (The owner drives the process.)

In manufacturing : the manufacturer is driving everything, the owner is not involved in the process.

The purchase:
In manufacturing the transaction of purchising is based on a finished product. and the transaction is done once.
In construction: the owner purchase several times, he purchased the design , planning ..contract for construction. The purchase is done several time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In maunfacturing my big challenge is to know what people want and to be able to deliver before my competitors

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Real estate companies are construction not manufacturing companies but they are close to manufacturing because we still have the process

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The challenges in construction is to articulate what i really require in clear terms and to be able to respond to their questions

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Construction company are in full control of the project

A

To enter the site u need to have approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The first thing in project development (Construction) is

A

need assessment (why i need to construct this thing like a building in AUB for example)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The seconf thing is a cost estimate and feasbility of the project

A

The cost estimates are not that accurate (very rough estimates)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Third we will have conceptual designs

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

After that we will have detatILED DESIFN THEN BIDDIING THEN CONSTRUCTION

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

NOTICE TO PROCEED

A

GREEN LIGHT TO START AFTER I SELECTED U TO THE JOB (THE CLOCK START TICKING)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

COMMISSION AND HANDOVER

A

OWNER SEE IF REUIREMENTS ARE MET

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

OPERATIONS ( BUILT FACILITY EXIST)

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

technology aspect of the project (Construction method statement)

A

diocument that describes the product that weill be built and the methodology and how to organize the site , the safety ,, operation of equipment like crane
example like the crane when the masri building was built

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Also there are specific method statement that will be delivered through out the project

A

true

17
Q

Management aspect of project

A

the 4 ms (materials , money, machinery, labor)

18
Q

Who are the key players in the construction project

A

Owner, deigner, contractor.
Interaction ( there are contracts between owner and designer, and a contract between owner and contractor.
although no contract between designer and contractor however there is interaction between them clarifications and questions)

19
Q

other players

A

subcontractors (hired by contractors, they are specialized subcontractors)
supppliers of the materials ( contractor buy most of them)

20
Q

technical issues that we face in projects

A

design , capacity….

21
Q

Qulaitative problems and issues ( more difficult to pinpoint responsibility)

A

like labor relations, safety of site , forms of contracts