lecture 12 Flashcards

1
Q

WE will talk about the technical studies that will be done on the planning phase

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Liquidated damages

A

should contractor be late on delivering the project , penalties willl be imposed, they are clalculated bu knowing how much lost/cost wil be imposed by not opening by that day

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

every project will go through a preproject planning phase

A

what type of facility i will build
what function it will serve
what objective it is serving and what is its scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what types of studies that are need ed in the planning phase

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Firsst type of studies is the project local

A

is it at the country level, or regional level, or discret level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Also kind of facilities that i wanna have

A

Like if you are having a real estate project , i the 1980s you will have large facilities, know u will have small ones

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

ALso type of construction

A

Cast on site construction
or
modular construction (prefabricated modules)
faster, much easier if you have space limitations.
Disadvantages : More expensive, lifting of high loads into place (technical requirements), Not flexible as cast on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Also. are there contractors for the type of the projects

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Availability of suppliers

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Availbaility of suppliers

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Site information

A

topography conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

These studies are donr by consultants or by design firms

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A lot of geotechnical studies are done on the design phase, however there are some geotechnical studies that are done on the planning phase

A

true

like topographic maps, sites around, previous projects, vegetation…

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In the design phase u divide the site to a grid and u decide upon the digging places

A

true

u need to know type of soil to know bearing capacity, slope stability, water level , cavities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

After that these information will be given to the contractor , however the contractor will have 90 days to do his own geotechnical studies (More detailed in order to confirm the design , if it is different than the designer they will change contracting terms)

A

true,

the designer will do geotechnical studies in order to have input for designing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Also, a traffic impact assessment will need to be done to see how traffic will be afffected

A

true
Impact of the project during construction phase and during operation phase
additional volume of cars

17
Q

Power and water sources

Energy sources

A

Will I need my own generators, will the public load hold

18
Q

Also environmental feasability impact assessment, emissions and pollutions
Effect on ecosystem (for example in dams

A

true

19
Q

Carbon footprint

A

how amount your activity have carbon emissions (burning fossil fuels)

20
Q

U have embodied footprint

A

every material has embodied CO2, during manufacturing and during tranportation

21
Q

U have operatinal CO2

A

during the operation , i am consuming a lot of energy and thus emiiting a lot of CO2
U can forecast that by energy modeling

22
Q

In order to reduce CO2 footprint

A

use recycled materials, use smarter technologies in production

23
Q

LCA assessment (life cycle assessment

A

through out the life cycle of the project and facility , you are assessing it is impact (embedded and operational)

24
Q

Also i will have economic feasbility

A

profits, benefits, costs,

bigger than financial (like parks have recreational benefits for people, fixing roads reduce mortalities)

25
Q

financial feasability

A

pure cas in cas out, pure financial dollar terms

26
Q

value engineering

A

optimize the design of the facility considering all the life cyles (building ,operation , maintenance) it is done by function analysis by listing all the functions and optimize the required function of my product with respect to the amount of money invested/ most cost effective way.
You have proactive value engineering that is in the planning and design phase ( optimizew my design)
Also i have a reactive value engineering, owner can no more afford during construction , so i reduce size of project

27
Q

proactive is better because i have more control on the projector

A

true

28
Q

Value engineering is done through planning, desing and construction

A

true

29
Q

value engineering can be done in weighted matrix example presentq

A

true