Midterm review Flashcards

1
Q

The client shall opt for multiple prime contractors when the project is

A

Large

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The client shall opt for the design build approach when the project is

A

complex

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The client shall opt for the CM approach when the project issue is

A

time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The client may engage the ———- before the design phase in preparation for the tender documents and launching of the bidding phase

A

Project manager (PM_

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The client may engage the PM(Project manager for the onset of the project life cycle (from the beginning during the pre project planning phase

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Enaging the PM earlier than the start of the construction will yield important benefits to the client not marginal ones

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Phasing the D-C (Design construct) process is not the major determinant for selecting the design build approach, the main determinant is the complexity of the project

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Phasing the Design construct approach (DC) is a by product of having opted for the design build approach

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The dominance of the designer is undermined by the constructor under the design build approach

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Planning for the undertaking of a construction project by the client will include deciding on the project oganizational structure prior to project go-ahead milestone

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Planning for the provisioning of a construction logistics by the general contractor to support work done by the subcontractor is undertaken by the general contractor prior to start of construction

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The role adminstrating the construction contract is:

A

1) responsibility of the A/E when PM is appointed but it becomes responsibility of the CM when CM is appointed
2-) Is not only boundedd to time and cost
3-) It primary deals with cost and time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Control is exercised by the CM over trade contractors

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Control is NOT exercised by the CM over the A/E

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Coordination is exercised between CM and the A/E

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The tower crane can be the source of major scheduling problems on site

A

truee

17
Q

The tower crane is not supposed to serve every spot on the construction site

A

true

18
Q

The contractor construction supervision team is more critical to the constructiion process compared to the A/E construction supervision team

A

team

19
Q

Involvement og human element in the construction process makes room for subjectivity related issues that can be detrimental to the project chances of success

A

true

20
Q

the world “heavy” constuction is

A

a) not reference to the amount of money to keep the construction going
b) is reference to the size of rock eaters that are used in tunneling operation
c) is not reference of the size of the foundation for a building tower crane

21
Q

Having selected a contractor on a lump sum basis normally show

A

1) the client want to set a firm budget for construction
2) Doesnot mean the client had insufficient confidence in the A/E capabilities
3-) Doesnot mean that the cleient has no use of bill of quantities during the constrution phase

22
Q

Under the CM (construction manager ) approach an overall design-construction duration reduction is highly possible not the construction duration ( intead the overall duration)

A

true