Lecture 20D Flashcards

1
Q

We use simulation techniques to model activities on the site like crane movement load…..

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What we want to do is graohical representation of the tasks when they are going to take place

A

WE want to have the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

we said to get to that we break down the WBS to get set of activities
Next we study the sequencing , which is the predecessor of which (types of dependedncies, finish to start…..lag)
Then i start deriving the schedule if i Know the duration of work

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Determining duration

A

What affect duration of work

DUration is driven by productivity and quantity of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Productivity is affected by several factors:

A

Weather
Experience of workers
Resources time (Equipments productivity)
Method of work (More strict tolerances , more time doing the work)
Working hours schedule (how many hours and days people work)]
method of statement
crowdiness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Working double shifts (like having 2 crews one from 8 to 5 and one from 5 to 2 am) affect productivity because of the handover

A

true , each crew have to figure what the other crew did

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Working during night times is less productive than day times

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The formula to get the duration is simple

A

quantity of work / productivity

We express productivity per crew not per worker, because work is done by crew

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The difficulty is to get the productivity

Quantity u get it from BOQ, it is usually up to 10 percent exact

A

Productivity s diffficult to get because of all the factors mentioned above
For example in lebanon, now we get strikes , which will affect productivity…many things psychological

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

So in order to get productivity we make assumptions

A

We assume it determinstic and constant
( I think of all what i have factors that afffcect my productivity and I deduce a productivity like 10 units per day per crew)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Most schedules are developed using single points estimates of productivity

A

true

this is a big assumption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If i have a problem in productivity, I may have problems at the individual levels so ilook there and analyze also there might be other problems

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

productivity starts lower at fisrst then improve in repetiitive acts

A

like the crew installed 2st window in 4 hrs, seconf in 3 anfd half, thirs in 3 hrs, 4th in 3hrs…..
Becuase they kniew the steps , place of materials, sttructure and weight
(Learning curve concept, leARNING SITE CONDITIONS)
Like if i have 100 winfows the average will be 3 hrs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Repetitive tasks are best to track productivity

A

true , as we tracked in the windows case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If the same workers moved to a new project with different contractor and different site

A

Probaably they will start at 5 because of the site conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Time is the result of knowing the quantity of work and productivity(crew)

A

true

17
Q

What if we have multiple crews, one that moves materials , other order and other install

A

I need to understand each of the taske , and i will have productivity at microlevel and at macrolevel
I will need to do simulation ( software.)

18
Q

For transportation and quieing we do simulation as that in the summer course

A

true

19
Q

To be able to get data on productivity , u need to start on data on maximum potential ideal productivity, then starts to apply factors

A

true

we make adjustment to maximum ideal potential productivity

20
Q

When have multiple crews , productivity might be dependent so u wont be able to account for it (like competing for crane

A

true

u will need to develop factors

21
Q

Productivity data best comes from previous experience

A

true, contractor with database will perform better in estimation