Lecture 18D Flashcards

1
Q

Consider a schedule for a project that will take one year , we start by january 2019 to Fininsh in December

A

When we finish the first the month , we realize we wont be able to finish on time then we postponed for onee month to finish, at the end of second month same has happened we postponed for another one month . This means that we have poor planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

This mean we didnt have due diligence in planning

A

we didnt have a robust plan, We didnt understand and analyze enough the work we wanna do

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Due diligence

A

means understanding the work to be done and the ways that it will be done with to (machines , productivity, sequence…)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Way of approaching is done by :Work break down structure (WBS)

A

Tree like structure that explains the work.
For example to build a buildig I shall work on 3 things :
Site prep, underground structure, and above ground structure
Under each one there is activities
Like in site prep u have shoring
In underground u have foundation…

So u will have levels of activities to do

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The benefits of WBS ( work break down structure)

A

1-1st u will get activities
2- u will use activities to creaete schedule
3- u use them to find the quantities and thus to find cost
The cost is made up from materials , labor (hrs of work, and wage and productivity)
, and i had overhead cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The process of cost estimation and scheduling and planning are inter-related

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Planning and control takes place in all phases of the project not only in construction

A

true, it takes place in planning (feasability, budget, cost…), design(value engineeering..) , bidding(control the cost) and construction (planning for the construction to control cost and increase profit..)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If i draw the control curve for the client on the project it will be decreasing

A

in planning i jhave a lot of control ….when construction starts i dont how much it gonna cost any more i lose a lot of control (I commit to the pproject)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

project control is a continuous proccess there is always update

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If my CEO ask me how the project is going

A

there is
cost
schedule
safety

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

For the CEO u will say we have a project for for 100 dollars and we are trying to finish for 85 dollars

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

when u are sitting with the construction manager

A

u list for him all the activities , and u tell him that those finished costed that much and those in progress we report spent (how much we spent until now) and we have forecasted , how much the forecasted cost will be .

For each activities we will see whether we finished it at budget , or under budget or over budget
This is called variance analysis-gap analysis ( u see the gap between the actual and the real)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

U also do cause effect analysis

A

like if u have overbudget run in some activities , u see what is the cause of this overcost and how it will effect me

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The above is called cost control

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

i Also do the same analysis for shcedule

A

I will have forecasted duration, actual duration , and forecasted duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Also for the project i have safety, but analysis is much simpler (Here we are quantifying safety)

A

here i report accidents ( I have levels of matrics) highest matrics is fatality.
also u have
Record of incidents rates : Number of incidents u have for every 200,000 workhours.
What is an incident: it differs , like in canada, if i slip due to water in ground it is considered an incident and it is reported.
In gulf it is not considered an incident

17
Q

Also we have lost time incidents rates (subset of record of incident rate)

A

Meaning incidents that happpen and cause lost time (like when i slippped it didnt cause lost time)

18
Q

How do we quantify quality

A

Record number of rejections for completed activities ,
also number of rejections for the submittals
also count the non performance reports ( theA/E inspected something u installed and reported that it will not be able to perform and it requires to be redone.

19
Q

An important point for scheduling is how much time is spent doing a work and how much work is done during this work (productivity)

A

true

20
Q

Basis used to measure performance of project

A

people usually use work hour (man hour):
I have 1000 hours to complete a work.
If i reach 500 hrs I look how much of the work i completed.

21
Q

Earned value annalysis

A

We
WE plot the time vs value of work ( spent , earned(value of completed wok))
We saw if we are earning more or spending more
Also i plot planned time vs earned time to see if i am behind schedule or ahead of the schedule

22
Q

How do we determine the earned value

A

We look atr the activity, and we see how many subactivities it is made from, and we see how much contribution of each of these subactivities to the main activity ( like if u have a column, u know you will have rebars, concretet., curing.), and i see how much of these subactivities are done and based on that i see how much earned value of the activity i have. (I may do weighted average of the subactivities because some are more main and important than others)

23
Q

When i draw the plaaning curv,

A

when i get the job

24
Q

when i draw earned and spent curves

A

at end of each month

25
Q

What happens when I have a change order ( like to add one span)

A

It depends on the change and how much it will effect , it can lead to change the baseline schedule and cost….

26
Q

I have something that is called trend analysis , meaning i look at my progress from 3 months i am late 40 % , i look now i am late 10% the trend is positive and vice versa

A

It is important for forecasting , u willl know u will finish in time and vice versa
it is a forecast based on the trends
It can give early warning
Based on that u take decision. Project control

27
Q

At end of the project u do a final analysis with the final data to benefit for future projects

A

true