Lecture 10 Flashcards

1
Q

which contract type with which delivery method

A

Any contract type ca be used with any deliverably method , it depends on the project and situation
i can do also combinations of contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Construction is a project driven industry

A

big dimension is the contractual nature

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The one who the most contract on the project is the contractor

A

true

I have contract with client and several contracts with subcontractors and suppliers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

i can impose on my subcontractors back to back contracts

A

I apply same terms and conditions by the owner regarding schedule payments, like in order to get paid u submit me a request i review and when approved i will pay u when clients do .
Meaning mirror the contract between me as a contractor and the client with that between me and the subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contract

A

Agreement between two or more entities to do something in return for a consideration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

purpose of contract

A

.the job is done for exchange
.there is penalty legallhy if u dont keep ur part of the contract
.contract can be verbal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Mostly all contracts are written also in large projects they are standardized

A
true
like fidic contracts
provide international standards
definitions
contract engineer 
......
In USA there are AIA contracts
Everything is defined in contracts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

we use standard contracts so we dont do everything again from start

A

also we can modify the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Contracting process in construction is very unique

A

The setup present in the contract can nott be created again even if i have the same entities , i will have different subcontractors , different regulations….

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In construction u buy the product i.e. project in bits and pieces

A

1st u buy concept then design then the bid then the tasks completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

U have general condition for the project

A

duties of entities , mechanism of payment; they apply over all project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Supplementary conditions

A

like liquidated damages; should u dont deliver on time , you will pay a penalty
Owners use LDs (liquedated damages to cut the price of additional work)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The most common type of contract in construction is

A

competitive bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Another way which is not used a lotis cost +fee

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

we also have unit price which is used also

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In the invitation for bidding i may have specific requirements like expertise , CVs of engineers…, they may ask other people they know if u are claim conscious contractors
gaurantee to handle financially the project

A

true

17
Q

claim conscious contractor

A

will review the project , identify the problems but dont talk about, then he will bid low, then when problems arisse during construction he will claim more
He doesnt raise the flag
He will bid perposely low and he will make more money due to variation order because of unidentified problems

18
Q

owners can prequalify the contractors

A

true

19
Q

How lump sum is made by contractors

A

he checks the BOQ and put expenses plus profits
He will just give the final number to the client.
Client can ask them to break it down like how much excavation, concrte, finishing

20
Q

We have direct costs

A

like materials and worjkers

21
Q

indirect

A

like engineers , crane

22
Q

lump sum gives the client a piece of mind about the cost

possibility to fix the cost

A

true

23
Q

Disadvantages

A

u may be paying a lot because the risk is high on the contractor
ALso as a client u are not flexible to change i lose leverage of bidding

24
Q

the secoond most used type is unit price

A

here u do the same as u did in the lump sum but u give them a chart of how much each item will cost like steel conncrete everything
units prices
It take out the risk of quantity fluctuation

25
Q

In unit price u have economy of scale also

A

like if the contractor do more jobs then client will tell him that is more work , u need to charge me little more than stated and vice versa

26
Q

Most contracts will have a lead of negotation if quantitits differ by 10 %

A

Both will raise the flag

27
Q

Advantages of unit price

A

more flexibility
risk for quantity variation will be reduced
if i do have fluctuation in quantities like excavation it will be beneficial

28
Q

Disadvantage there is no fixed price

A

true

29
Q

Disadvantage ( Bid unbalance)also i my price higher of units for early works so i can push the curve the left

A

true
clients may give advanced payments to decrease this behavior in return they get a gaurantee for that because they become cash exposed

30
Q

Cost plus fee type of contract is a fully reimbursable type of contract

A

keep alll the bills , i will pay them in addition to a fee

31
Q

Cost plus fee it is risk free

A

also it is lucrative for the contractor if it is a percentage for the cost so contractor will start trying to raise the cost for more fee

32
Q

clients can do a fixed fee like u will get 10 percent of 1 million

A

ur fee is a lump sum

33
Q

Also client can place a maximum price plus a fee after which the client no more pays

A

hybrid

cost plus fee to a certain point then it will get to be lump sum

34
Q

Also u may have incentives

A

if u end less a target u will split the saving
the same if above
share pain and gain

35
Q

cost plus fee

A

when u have a lot of uncertainties and it is a fast track also fuulyy transpareny

36
Q

disadvantage

A

no fixed budget

u need army of controllers on contractor