Case Study Flashcards

(6 cards)

1
Q

You mention in your approach that the high water table was discovered during RIBA Stage 4, what would you suggest for future projects to mitigate risk in the ground?

A

Undertake Ground Investigation at an earlier stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You note that you collaborated with the structural engineer to develop a design proposal, what part did you play in this?

A

My roles to the understand the design proposal and advised on the cost impact.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

You mention in option 1 that you advised on a rate of £70m2 for hardcore, how did you calculate this rate?

A

I reviewed the requirement and benchmarked my rate against retained prices from project with a similar scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

You mention in option 2 for the bore pile solution that you included a 5% construction risk, please can you describe some examples of what this is likely to cover?

A

Any unforeseen ground conditions resulting in additional ground remediation works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

You mention in option 1 and 3 you said you established the construction periods. How did you do this?

A

For option 1, I liaised with the project manager to determine a suitable duration allowance for the works, for option 3, I spoke to a specialist contractor who was able to advise on a programme duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In Table 7, you discuss the load bearing capacity of CFA and helical piles, in practise would you advise a client on the load bearing capacity of structural elements?

A

No, I would refer the client to the structural engineer for this advice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly