What is internal control?
Contractor, or party constructing/producing the product (I check up).
What is external control?
Control imposed from a client, user, stakeholder (Someone else check up on me).
What is schedule control?
Keeping a project on schedule. Apply a buffer strategically to ensure realistic completion dates and times [Fever chart - graphical representation of how the project is doing].
What is project monitoring?
The process of tracking performance - discover lacking areas, uncover potential problems, and keep project moving towards target.
Name five methods of project monitoring.
Status review meetings
Observation / site meetings
Technology
Formal reports
Document management
What must a communication plan include? And how does a formal one differ from an informal one?
Schedule for project reviews
Milestone meetings
Important points of contact (customer/contractor)
Formal - reports to top management / project managers / customers.
Informal - through the grapevine.