Contract Administration Flashcards
(21 cards)
Can you explain how you would implement a change control procedure in D&B?
Use the change control procedure set out in the contract
- D&B contractor would submit a CRF to myself and the EA
- EA agrees whether change
- I then agree cost and recommend to EA
- EA gets approval from Client and then issues an instruction for the change.
What are the dangers of working on a bespoke contract?
It’s bespoke so less understood to all parties. Great care must be taken when administering
Role of Contract Administrator under JCT?
- Administers the construction contract
- Must act honestly and reasonable
- Issues instructions & EOT
- Certifies sums due
- Assesses delay and grants time and cost relief
How does the role of Employers agent differ from contract administrator?
- EA is seen as clients advisor
- Required to protect clients interest (CA must act impartially)
What is Practical Completion?
The works are generally considered to be practically complete when there are no outstanding defects and the building can be put to its intended use.
What would you do if the contractor has not completed by the pc date?
- Advide CA/EA to issue non completion cert
- Client must give notice 5 days before final payment if they intend to deduct LADs
What is a pay less notice
They intend to pay less than the payment notice or contract value
What must a contractor issue at PC
Operation and Maintenance Guides (O&M)
Health and Safety File
What would you do if some defects aren’t completed at end of defects period
- Defect Schedule (Identifying defects)
- Contractor to complete in reasonable time
- If done, cert if making good
- If not, monies deducted from remaining retention - breach of contract
Partial Possession challenges
LAD’s to be reduced accordingly
1/2 retention released for that part (could be hard)
Contractor has not programmed for it.
What does CA do at partial possession
CA issued notification of partial possession
What does CA do at Sectional Completion
Certificate of sectional completion
What is a defect?
Works that have been completed but not to an acceptable standard
How can an employer deal with a Latent Defect
- Lat defects not enforceable by contract
- Client can seek redress through breach of contract (6 or 12 years)
Defective Premises Act 1972 - Seek redress for damages through breach of contract, or for negligence
The Latent Damage Act 1986 - provides the claimant with three years, from the date when they knew or should have known or a problem, to issue proceedings.
Expressed terms and Implied terms
ET - Terms expressly agreed between parties - usually wrriten in contract
IT - Not expressly agreed in contract - implied by either common law or statute
What is risk appetite
Level of risk an organisation is willing to take to achieve their objectives
Can you rescind a PC Cert
No, remains final and binding
Client role under JCT
- Make payments
- Provide possession of site
- Not hinder contractor contractor to do works
MC role under JCT
- Construct works in accordance with contract
- Carry out works dilligently
- H&S
What takes precedence - ERs or CPs
ER
On JCT, if a change cannot be agreed, what do you do?
Valuation of a variation in accordance with the Valuation Rules
Imposing a valuation is not a favoured option
MW - if no agreement, CA to make fair assessment