Contract Administration Flashcards

1
Q

Can you explain how you would implement a change control procedure in D&B?

A

Use the change control procedure set out in the contract
- D&B contractor would submit a CRF to myself and the EA
- EA agrees whether change
- I then agree cost and recommend to EA
- EA gets approval from Client and then issues an instruction for the change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the dangers of working on a bespoke contract?

A

It’s bespoke so less understood to all parties. Great care must be taken when administering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Role of Contract Administrator under JCT?

A
  • Administers the construction contract
  • Must act honestly and reasonable
  • Issues instructions & EOT
  • Certifies sums due
  • Assesses delay and grants time and cost relief
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How does the role of Employers agent differ from contract administrator?

A
  • EA is seen as clients advisor
  • Required to protect clients interest (CA must act impartially)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Practical Completion?

A

The works are generally considered to be practically complete when there are no outstanding defects and the building can be put to its intended use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What would you do if the contractor has not completed by the pc date?

A

If I were acting as either the CA or EA I would advise the client to issue a non-completion certificate.

If date fixed after the notice then date cancels out the notice. Issue another if necessary. Client must give notice of intention to the contractor to deduct LAD’s. 5 days before the date of final payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a pay less notice

A

They intend to pay less than the payment notice or contract value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What must a contractor issue at PC

A

Operation and Maintenance Guides (O&M)
Health and Safety File

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What would you do if some defects aren’t completed at end of defects period

A
  • CA to issue defect schedule and give instruction to contractor to complete within 7 days.
  • Do not issue certificate of making good at this point.
  • If still not complete then cost the remaining and subtract from retention.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Partial Possession challenges

A

LAD’s to be reduced accordingly
1/2 retention released for that part (could be hard)
Contractor has not programmed for it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does CA do at partial possession

A

CA issued notification of partial possession

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does CA do at Sectional Completion

A

Certificate of sectional completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you explain what is good practice with regards to latent defects as a CA?

A

If a latent defect are discovered after PC and during the rectification period
* Contractor will be liable for direct costs reasonably incurred by the client as a result
* This will include the cost of any appropriate remedial works and also any loss of profit or such like reasonably suffered by the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a defect?

A

Works that have been completed but not to an acceptable standard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How can an employer deal with a Latent Defect

A

Latent defects are outside of terms of the contract and not enforceable by the contract, however the employer can seek redress through breach of contract. 6 years for underhand and 12 as deed..

Defective Premises Act 1972 - Seek redress for damages through breach of contract, or for negligence

The Latent Damage Act 1986 - provides the claimant with three years, from the date when they knew or should have known or a problem, to issue proceedings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly