Project Finance Flashcards

1
Q

You have mentioned interim payments, can you please explain the timescales for payments with regard JCT (standard and D&B)

A

No less than 7 days before due date- MC issue valuation (D&B - Val is up to due date)

0 days - Due date
+5 days - CA Issue payment cert
+ 9 days - Client issue a pay less notice
+14 days - Final date for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a provisional sum

A

An allowance included for:
* Not sufficiently defined, designed or detailed to allow accurate costing
* Work that employer may / may not want carried out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the importance of a cash flow forecast?

A
  • Gain understanding of financial requirements
  • Check against valuations
  • Plan expenditure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of providing clients with financial statements?

A
  • Provide financial overview for client
  • Inform likely outturn cost of project
  • Understand potential savings / additional funds
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the JCT Standard Form ‘Valuation Rules’?

A

Contract Rates: where work is of similar ‘character’ to work in the original Contract Documents then the valuation of the variation shall be consistent with rates, prices or amounts of work in the proceed document.

Fair Rates and Prices: Where work is not of a similar ‘character’ then it should be valued at ‘fair rates and prices’.

Dayworks: Method of valuing work which cannot properly be valued by measurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Considerations when advising client on Cashflow

A
  • Holidays (eg winter / xmas)
  • Retention (end of defect period)
  • Certification period
  • Payment period
  • Sectional completion / Partial possession (Retention)
  • Risk
  • Prov sums
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Reasons for variance in Cashflow

A

Lower
- Site conditions
- Adverse weather
- Programme issues
- Various delays

Higher
- Front end loading
- Variations
- Ahead of programme
- Distressed contractor
- Cashflow not accurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What would you include in a cashflow in addition to the direct cost of the works?

A

Retention
Variations
Prov Sums
VAT (maybe but complicated)
Materials on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What would you omit in a cashflow

A

Anything as long as noted to the client
VAT
Materials off site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Effect of Loss and Expense Claims on Cashflow

A
  • Update for best and worse case LOE additions
  • May include EoT if necessary
  • Update for when claim will be paid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Effect of Liquidated Damages on Cashflow

A
  • Dont include until agreed with contractor
  • Doesnt act as saving as it is genuine loss client has received - balances out
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Effect of procurement route on cashflow

A

Traditional
- Separate construction costs from design fees and risk allowances

Design and Build
- Include element of design fees and risk allowance into construction costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why do you think a cash flow forms an S’Curve?

A

Enabling works cost little then bigger packages such as steel and superstructure, costs then reduce towards end for finishes and fit out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is change control procedure JCT

A
  • Contractor notified of change
  • Contractor issues variation
  • QS to review
  • 7 days to notify if not agreeable, if is then CA instructs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the JCT timescales for submitting a Final Account

A
  • Contractor should submit by maximum 6 month
  • Final account should be agreed in 3 months following issue
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What should be issued with final accounts

A

Substantiation to variation figures
Sub contractor quotes
Daywork sheets
Loss and expense claims with build up
Build up of fluctuations

17
Q

How does NEC deal with provisional sums

A
  • Unamended NEC doesnt provide use of prov sums
  • NEC approach - if unclear and price cant be provided, item excluded until defined
18
Q

Can contractor claim additional prelims or EOT when firming provisional sums

A

No, if defined it should have been allowed for in programme and prelims

19
Q

Contractor has made large and in your opinion unrealistic claim for L&E, how would you deal with it

A
  • Highlight concern with figure submitted
  • Assume CA has agreed claim is valid, carry out due diligence checks and assess
  • Update client regularly until resolved
20
Q

Who prepares Final Account

A

Traditional QS
D&B EA

21
Q

Procedure for agreeing final account

A
  • QS to visit site to evaluate if required
  • Once prepared, QS sends all details and supporting evidence to MC
  • Disagreements to be discussed and negotiated
  • Both parties to sign summary to show agreement
22
Q

What is cash flow projection

A

Shows predicted flow of cash in and out of project

23
Q

What is pay less notice

A

Gives paying party right to pay less