Risk Management Flashcards

(28 cards)

1
Q

What is RISK

A

Uncertain event that if happens will affect the outcome of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is difference between a hazard and a risk

A

Hazard: something that could potentially cause harm.
Risk: the degree of likelihood that harm will be caused

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Types of risks (Management of Risk)

A
  • Avoidance - Risks with such serious consequences they should be avoided all together (redesign)
  • Reduction - Level of risk unacceptable, actions taken to reduce (more site investigations / use of different materials)
  • Transfer to contractor - Risks that may impact programme transferred to another party that may be better at managing it (pay premium)
  • Sharing risk - When risk not wholly transferred e.g. provisional quants, pricing risk to contractor, quantification risk to client
  • Retention - Risks retained by employer, appropriate risk allowance made in cost plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Risk categories in NRM1

A

**Design development risks **
- Allowed for during the design period
- To provide for design development, changes in estimating data, third party risks (eg planning requirements), statutory requirements, procurement methodology and delays in tendering
**Construction risks **
- Allowed for during the construction period
- To provide for risks associated with site conditions, ground conditions, existing services and delays by statutory undertakers
**Employer change risks **
- Allowed for during design and construction
- To cover the risk of Client changes (eg changes to scope, programme, quality)
**Employer other risks **
- Allowance for other employer risks (early handover, acceleration availability of funds/postponement)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Risk Managament Process

A

Risk Identification
Risk Analysis
Risk Response
Risk Manage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk Managament Under JCT and NEC

A

JCT Risk - Risk allocation, Insurance requirements, Design responsibility, Provisional sums
NEC Risk - Risk register, Early warning, CEs, Collab approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How can a client minimise design risk

A
  • Use trusted experienced design team
  • Transfer the risk (D&B and CDP)
  • Effective management of risk register
  • Early contractor involvement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a risk assesment

A

Assesment of risk to understand liklehood and impact of them occuring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What recourse is there in the contract to reduce client risk?

A

Collateral Warranty
Bonds
LAD’s
Third party rights
Dispute guidelines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Are you familiar with a risk register? Whats in it?

A

Risk
Liklehood
Impact
Cost Impact
Mittigation
Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do you start a risk register on a project?

A

Organise a risk workshop to identify the risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Under a NEC form of contract what is the relevant of a risk register?

A

It is a contract document along with the programe.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How would you allocate a risk owner for a risk item on a risk register?

A

By whome is best to manage it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How should risk be allocated

A

The person or party best placed to manage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How often do you update risk assesment

A

Every time you go to site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a nominated subcontractor (how does risk work)

A

Nominated is selected by the client, they are part of contract docs and client has risk as they have insisted.

17
Q

What is a named subcontractor (how does risk work)

A

Named or preferred by client but MC has risk.

18
Q

What is the difference between a contingency and a risk allowance? And which one would you recommend?

A

Risk allowances are the “known” unknowns, such as underground utility conflicts,
Contingencies are for the “unknown” unknowns, such as changes in a project’s scope.

19
Q

Why are early warnings important on NEC

A

Address potential risk before escalation - could affect TCQ

20
Q

Key benefits of effective risk management

A
  • Increased confidence acheiving objectives
  • Reduce cost time overruns
  • Workshops can encourage communication
21
Q

How can project team reduce design risk for client

A
  • Use trusted experienced team
  • Trasfer design risk in procurement e.g. CDP or D&B
  • Effective and regular management of risk register
  • Early contractor involvement
22
Q

General risk categories

A
  • Political and business risks (client share price down due to delay)
  • Benefit risks (Compliance with planning may limit size of scheme)
  • Consequential risks (risk that occurs due to other risks, no power)
  • Project risks (affect delivery of project, TCQ)
  • Programme risks (affect job as whole funding)
23
Q

Why quantify a risk

A
  • Build risk allowance
  • Client may need to report upwards
  • Project forms part of larger programme of works
  • Provide comfort to funders / third partys
24
Q

A typical risk management strategy would cover

A
  • Whos responsible
  • How risks will be identified
  • Frequency of meetings
  • Reporting forms
  • Software tools and techniques used
25
Risk breakdown structure (RBS) 7 risk environments
* Natural * Economic * Governmental * Societal * Client * Construction * Project
26
Risk identification techniques
* Brainstorming * Historical information * Industry knowledge * Lessons learned * Workshops
27
Risk Catergories (Other)
* External (uncontrollable) * External (Controllable) * Internal - Client operations (Controllable) * Internal - User requirements (Controllable) * Internal - Project processes (Controllable)
28
What is Qualititive analysis
* Prioritises risks in terms of imporance * Should be carried out in early stages of risk management * Done by multiplying likelihood and impract