KEY ISSUE ONE Flashcards

(9 cards)

1
Q

KI1 - What was allowed for in the contract in terms of the basement space?

A

GIFA was roughly 44m2
Height was roughly 1.99m

GIFA to be roughly 35m2
Height to be roughly 1.83m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

KI1 - Did you provide costs for all three options?

A

Option 1 - 60k
Option 2 - 75k
Option 3 - 30k (saving in basement propping - 2 weeks)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

KI1 - The basement was infilled, how was this done, and were there any structural considerations in relation to this?

A
  • Break out existing slab
  • Formwork created at pile locations
  • Mass fill concrete basement level
  • Imported fill & compact to pile locations
  • Formwork to ground beam perimeter prior to second pour
  • Fill from stockpiles
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

KI1 - How would unknown factors to the ground or ground conditions be dealt with

A

Contractor risk, no provision in an unamended JCT, follows common law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

KI1 - What were the trial pits and bore holes for

A

Bore Holes - Establsh pile design
Trial pits - Examine existing foundations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

KI1 - What was in contract for the basement

A
  • Undefined prov sum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

KI1 - Why did you have an undefined Psum for the basement

A
  • Extent of design wasn’t know
  • Couldnt gain access until it was propped
  • Needed contractor on site
  • Contractor not accepting defined psum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

KI1 - Why didnt the contractor price the options

A
  • Timing - Contractor would have taken too long (supply chain)
  • Time at large, needed to make a decision quick
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

KI1 - What were some of the items claimed in the L&E claim

A
  • People
  • Site cabins
  • Scaffold
  • Structural monitoring
How well did you know this?
1
Not at all
2
3
4
5
Perfectly