KEY ISSUE ONE Flashcards
(9 cards)
KI1 - What was allowed for in the contract in terms of the basement space?
GIFA was roughly 44m2
Height was roughly 1.99m
GIFA to be roughly 35m2
Height to be roughly 1.83m
KI1 - Did you provide costs for all three options?
Option 1 - 60k
Option 2 - 75k
Option 3 - 30k (saving in basement propping - 2 weeks)
KI1 - The basement was infilled, how was this done, and were there any structural considerations in relation to this?
- Break out existing slab
- Formwork created at pile locations
- Mass fill concrete basement level
- Imported fill & compact to pile locations
- Formwork to ground beam perimeter prior to second pour
- Fill from stockpiles
KI1 - How would unknown factors to the ground or ground conditions be dealt with
Contractor risk, no provision in an unamended JCT, follows common law.
KI1 - What were the trial pits and bore holes for
Bore Holes - Establsh pile design
Trial pits - Examine existing foundations
KI1 - What was in contract for the basement
- Undefined prov sum
KI1 - Why did you have an undefined Psum for the basement
- Extent of design wasn’t know
- Couldnt gain access until it was propped
- Needed contractor on site
- Contractor not accepting defined psum
KI1 - Why didnt the contractor price the options
- Timing - Contractor would have taken too long (supply chain)
- Time at large, needed to make a decision quick
KI1 - What were some of the items claimed in the L&E claim
- People
- Site cabins
- Scaffold
- Structural monitoring