Quantification and Costing Flashcards

(37 cards)

1
Q

Why did you choose a Schedule of Works for Central Annexe?

A

T - Quicker to produce, dont take off measures
C - Cheaper to produce, cost certainty based on design at tender
Q - Works simple in nature, didn’t require that level of detail
R - Risk with MC as they provide measures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

+/- BoQ

A

+ Simplifies tender analysis
+ Saves time and cost of contractors measuring
+ Better for valuations and variations

  • Client takes risk if wrong
  • Takes longer to produce
  • More costly
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

NRM1 - Brief overview

A

Order of cost estimating and cost planning for capital building works

Guidance on quantification of buildings works for preparing cost estimates and cost plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

NRM2 - Brief Overview

A

Detailed measurement for building works

For BoQ and Quantified SoW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

NRM3 - Brief Overview

A

Order of cost estimating and cost planning for building maintenance works

Guidance on quantification and description of maintenance works for preparing initial estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is BoQ

A
  • Breaks down works into exact quants measured in indutstry wide format (NRM 2)
  • Includes all components
  • Based on mature drawings
  • Contractors insert rates
  • Can be used for cost control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule of Rates

A
  • List setting out staff, labour and plant hire rates that contractor will use for pricing the works
    On a larger scale
  • When nature of work is known but cannot be quantified
  • or continuity of programme cannot be determined
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

+/- of SoR

A

Adv
* Variations easier to estimate and normally cheaper than fixed price traditional contracts
* Client can stop start work at a pace determined by cashflow
* Inexpensive and quick to tender for contractor
Dis
- Additional resource to measure
- No final price when committing
- Contractors may be tempted to front load (in case later work doesnt materialise)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is SoW

A
  • Lists the works required on a project
  • References the requirements included in the specifications and contract drawings
  • Plus any additional ‘builders work’ items
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Contract sum analysis and disadvantages

A

Mainly used in D&B, less detail than SoW
* Alternative pricing document
* Standard format
* Employers Agent creates to support the tender returns review
Dis
* Less detailed (one item vs multiple in SoW)
* Not suitable for valuations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

NRM1 Group Elements

A

Facilitating
Substructure
Superstructure
Internal Finishes
FFE
Services
Pre Fab Building units
Work to existing buildings
Prelims
OH+P

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a functional unit and how would you use this for cost planning?

A

Unit rate when multiplied by number of functional units gives total building works estimate

Minus prelims and ohp

Nrm1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How would you account for VAT in a cost plan?

A

VAT would be omitted as differing clients may get different rates applied (NRM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

You have clearly got a wide range of experience doing valuations, run me through an issue you have had during a valuation and how you overcame it?

A

Central Annexe - CSA
E.g. lump sum, how is this proportioned to all works (piling) - had csa on job and no breakdown, had to agree suitable split

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Give some examples of measured works on your projects and how you valued them?

A

Associated with BoQ - measuring carpet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why do we carry out valuations on construction contracts?

A
  • Increase cost certainty
  • Check against contractors application
  • Ensure works are progressing
17
Q

If the client is hoping for a quick pre-tender programme, what pricing document would you advise?

A

Schedule of Works

18
Q

How can works be costed

A

Lump Sum
Cost Reimbursable
Re-measurement
Target Cost
Guaranteed Max Price

19
Q

Lump Sum

A
  • Cost agreed at start of project. Can only be altered by formal variations.
  • Use when - Have detailed design (complex work)
20
Q

Cost Reimbursable (Cost Plus)

A
  • Contarctor payed actual cost + agreed fee (OH+P)
  • Use when scope is not properly defined and SOS is urgent (Emergency)
21
Q

Re-measurement

A
  • Costed using schedule of rates or approx boq and detailed measurment at each valuation.
  • Use when scope of works can be described in detail but the quantities cannot (Maintenance)
22
Q

Target Cost

A
  • Hybrid of cost reiumbursable and lump sum
  • Agree a price for the works
  • Subtract the actual cost and split the saving or uplift (pain and gain).
23
Q

What is a base cost estimate

A

Everything included but no risk, uncertianity or inflation.

24
Q

On your project, can you explain how you prepared the schedule of works?

A
  • Using the specification and drawings provided by the architect
  • Use NRM1 for elements
  • Preambles - Explanation of the document and instructions
  • Rate and quantity are blank
  • References drawings and specifications throughout to assist contractor
25
What are the roles of various people in preparing the pricing document?
Employer works with designer to produce spec and or drawings to be used by QS to produce
26
Dayworks
* Paid for instructed works * On basis of labour, materials and plant * Plus mark up for OH&P
27
Why is it important to measure works according to industry standards and best practices
* Provide consistency * Greater accuracy * Ensures all parties price same basis, reducing risk
28
How is risk dealt with under NRM
* Recommends that risk allowance is not standard percentage * Should be assessment of risk
29
Implications of overvalue or underevalue works (valuation)
* Val must be realistic assessment * Low val can create financial issues for contractor * High val risk to client
30
Key things to consider prior to valuing materials off site
* Request vesting cert * Check insurances until materials arrive to site * Ask for evidence they are for the project * Maybe look into bonds
31
How would you ensure value for money on day works
* Use time sheets * Check materials and use cost plans
32
How is change identified under JCT
* Alteration or modification of the design, quality or quantity of works (by change of ERs in D&B) * Imposition by the client of any obligations or restrictions (Acces site, limitation to space or working vhours) Change control and management PI
33
Is it not mandatory to follow procedures set out in NRM
No, however is allegation of professional negligence is made, court is likely to take account of docs published by RICS
34
How do you carry out valuations using a SoR
Quants unknown so these need to be verified before agreeing
35
Why did NRM replace SMM7
* Better meeting needs of client * Better method for quantifying risk * Provides more up front detail * Allowing better consideration of full costs of a project
36
What were items the contractor was claiming for that were not instructed
New carpets Had to reuse where necessary
37
What is the purpose of the RICS Codes for Measuring Practice
Standerdie and improve accuracy for measurements and descriptions