KEY ISSUE TWO Flashcards

(8 cards)

1
Q

KI2 - How did you get costs for the demolition works?

A

Used the contractors costs for demo on the one facade and adjusted to suit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

KI2 - You mentioned that the solution meant that there were more initial costs required early on – how did the client manage this in terms of cashflow?

A

Was discussed at the time but client was able to manage it. Balanced off against saving on inflation if to carry out in phase 3.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

KI2 - How much extra was the 3rd option to the 2nd

A

About £15k

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

KI2 - Option 2, how did you calculate the inflation for option 2? What information did you use? Which Indices from BCIS? Is this always correct?

A

BCIS
TPI - Tender Price Indices
Industry standard and used previous.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

KI2 - You mention that the abortive costs and prelims would equate to £20k vs a £40k construction cost by delaying the remedial works, how did you calculate this?

A

Mobilising and Demobilising access
Abortive cost - risk of delay/design changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

KI2 - How did you go about generating your risk allowances when working on a heritage building vs a normal new build project?

A
  • Shell & core only
  • Risk allowances based off reasonable cost estimates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

KI2 - How did you consider the planning conditions when working on a heritage building?

A
  • Not listed building
  • Conditions were to build back to original
  • No BREEAM requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

KI2 - What were the remedial works

A
  • Helibar works
  • Wall plate remedial
  • Re pointing
  • Clean
  • Lintel replacement
  • Broken bricks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly