Design Economics and Cost Planning Flashcards

(22 cards)

1
Q

What is inflation

A
  • NRM 1 definition: Sustained increase in the general price level of resouces
  • It is included as an allowance in order of cost estimates or cost plan for fluctuations in basic prices
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an order of cost estimate

A
  • Estimate based on benchmark data for similar type of project
  • Purpose to establish affordability
  • Takes place prior to preperation of full set of drawings or BoQ
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

RIBA Workstages

A

Stage 0: Strategic Definition
Stage 1: Preparation and Briefing
Stage 2: Concept Design
Stage 3: Spacial Coordination
Stage 4: Technical Design
Stage 5: Construction
Stage 6: Handover and Completion
Stage 7: Use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Difference between Order of Cost Estimate and a Cost Plan

A

Order of Cost Estimate
- Early high-level estimate
- Provide guidance to client in relation to their planned scheme
- Compare to available budget
- Typically prepared at RIBA stages 0 - 1

Cost Plan
- Detailed elemental cost estimate
- Takes quants from drawings to provide accurate cost estimate
- Typically prepared RIBA stages 2 - 4
- Should be used to support design team in designing to available budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can you explain term ‘Cost per functional unit’

A

Unit rate when multiplied by number of functional units gives building works estimate (excl prelims and OH&P)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can you name the documents in the NRM suite

A

NRM 1 - Order of cost estimating and cost planning for capital building works
NRM 2 - Detailed measurement for building works
NRM 3 - Order of cost estimating and cost planning for building maintenance works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Do you need a programme to complete the cost plan

A

Prelims typically presented as weekly rate, therefore programme of high level dates will be required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are some reasons we have cost overrun on a project

A
  • Ambiguous client brief
  • Unrealistic cost estimates
  • Project risk realised and not properly managed
  • Uncoordinated design
  • Unknown external factors
  • Inflation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How can the Cost manager help control design to keep within budget

A
  • Explain to team when the cost plan sits against the budget and discuss limitations
  • Identify areas of design which may not be economical
  • Regular project risk reviews
  • Contribute to VE or cost saving sessions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do you understand by the term benchmarking

A

Use of historical data from projects similar in nature as a comparison to check cost on project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Are you aware of value engineering and value management?

A

Value Engineering
- Method used to eliminate any unnecessary costs
- Achieve value for money on a project.
Value Management
- Method of highlighting possible opportunities to create value within a project
- Managing those solutions to ensure value is continuously delivered
- It encompasses the whole life cycle of a project, from design to completion and beyond.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you deal with a cost plan over budget

A
  • Communicate the matter to the client and team
  • Identify sreas where savings can be made
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What were the abnormal and identified exclusions you refer to on DWP?

A

One building had a safe room
Externals
M&E
Used standard allowances
Exclusions - Remediation of any existing building defects, Works to existing façade

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you go about providing cost for M&E

A
  • Used NRM1 principles
  • Market test
  • Liaise with inhouse M&E QS
  • Above allows me to make sure iv understood what is required and have made sufficient allowance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How does PTE differ from cost plan

A
  • Final estimate before tender
  • Allows cost to be produced in line with the pricing document to allow tender analysis
  • Cost plan includes all project details
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Types of inflation

A

Tender: Period from base date to date of tender returns
Construction: From tender return to mid point constriction

(As per NRM)

17
Q

Purpose of cost planning

A
  • Ensure clients value for money
  • Make client and designers aware of cost consequences
  • Monitor expenditure
  • Help client make informed decisions
18
Q

Can you talk about how you used historical data on DWP

A
  • Cost models using existing projects
  • Remember to use location time factors
  • Included approrpiate inflation
19
Q

What value engineering was suggested on DWP

A

Mainly reusing existing items (Carpet)
Reducing spec of high priced items

20
Q

What would you take into consideration when advising OH&P

A

Percentage
* Location
* Level risk
* Project type and value
* Market conditions

21
Q

What is optimism bias

A

Unconsiously downplay complexity on a project resulting in under estimates of costs

22
Q

Purpose of NRM

A

Provide standard method of measurement and cost planning across industry