Procurement and Tendering Flashcards

(28 cards)

1
Q

+/- Traditional

A

Advantages
* Retain control of design
* Completed design before tendering - tenders based on same thing
* Better price certainty entering contract
Disadvantages
* Longer duration due to pre contract design
* Design risk sits with client
* No buildabilty from contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When might Traitional be appropriate

A
  • Shortest programme not priority
  • Cost certainty is important
  • Employer has specific design requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

+/- D&B

A

Advantages
* Can SOS sooner
* Single point responsibility
* Harness expertise
* Design risk transferred
Disadvantages
* Relies on quality and detail in clients brief
* Premium built in for MC risk
* Harder to compare tender return
* Less control of aesthetics and quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When might D&B be appropriate

A
  • Need for early start on site
  • Complex projects may benefit from input
  • Minimise risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Normalisation

A

Ensuring tenders are like for like

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How would you Normalise

A
  • Avergae of submitted costs
  • Highest price from tender returns
  • Use cost plan allowance for that element
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Buildability

A
  • Ability for design to be constructed and maintained efficiently and safely
  • Refers to early pre contruction advice from contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Advantages of buildability

A

Improved efficiency in constuction
Can save time and cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What additional insurance might be required under D&B

A

Contractor and their design team will have design responsibility.
Additional PII may be required (design responsibility)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Procurement

A

Overall act of obtaining goods and services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Tendering

A

Method of obtaining price and resources necessary to carry out works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What decides Procurement route

A

Clients objectives and key drivers in terms of Time, Cost, Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Framwork agreement

A
  • List of contractors selected after formal tendering procedure to work over long period
  • Client continually commissioning construction work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

+/- Framwork

A

Advantages
* Repeat work
* Only negotiate once
* Time saving
* Collaborative
Disadvantages
* Doesnt always deliver value for money
* Restrict new suppliers
* Contractors can become complacent
* Public procurement regulations may impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why might Framwork be appropriate

A
  • Clients continuosly comissioning construction work to reduce timescale
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Process of Single stage tender

A
  • Typically carried at at RIBA stage 4 when detailed design available
  • Tender docs issues to competing contractors
  • Tenderers compete on identical information
17
Q

+/- Single Stage

A

Advantages
* Lump sum cost for all works
* Competitive pricing
* Used at RIBA stage 4 so full design
Disadvantages
* No input from contractors
* Relies on detailed thought out design and tedner docs
* Contractors may be unwilling to tender in good economic climate (too much comp)

18
Q

Process of Two Stage Tender

A

STAGE 1
* Client provides outline design - Contractors compete
* Chosen on quality of bid, quality of team, prelims and OH&P
* Preferred MC joins team on consulting basis using PCSA
STAGE 2
* MC influence design / buildability
* Contractor enters into detailed contract
* Negotiate final price, contract conditions and programme

19
Q

+/- Two Stage Tender

A

Advantages
* Early MC appointment to gain buildability input
* Earlier SOS (overlap)
* Increased opportunity to VE and identify risk
Disadvantages
* Lack cost certainty
* Additional fee for PCSA
* Potentials for negotiations to fail

20
Q

JCT Tendering practice note 2017

A

Guidance document on different tendering procedures
Preliminary enquiries
ITT and tender process
Assessment and award

21
Q

Why is it important to follow up with exclusions with tenderers

A
  • Fair comparison
  • Cost certainty
  • Qualification of tender - if the works excluded is required then it could invalidate their tender
22
Q

What is typically assessed on H&S element of tender

A
  • Construction phase plan (CDM)
  • Management of H&S on site
23
Q

How was quality assess on AHU

A

Methodology
Programme
H&S
Compliance with tender and contract conditions
Supply chain

24
Q

What is Base Date

A

Date from which:
Change in condition can assessed
JCT D&B states its 10 days before tender return date

25
Why single stage on AHU
* Lump sum cost for all works * Competitive pricing (ER) Aware that: * Contractor not fully understanding project may lead to higher risk * Programme implication to include tender period
26
Why not open tender on AHU
* Use tried and tested contractors * May deter competition if low chance of winning
27
What are the two alternative options for examanation and correction of tender returns
Alternative 1: Standby or withdraw (next lowest considered) Alternative 2: Confirm or ammend if genuine error (if ammend and not lowest, next lowest is considered)
28
Can you extend a tender period
Contractor can request extension Must be given to all PM to build float in case of extension May extend due to Contractor under estimating amount of work Current commitment Adenda being issued Or leaving too late