Contract Practice - NEC Flashcards

1
Q

NEC Options

A

Option A: Priced contract with activity schedule.
Option B: Priced contract with bill of quantities.
Option C: Target contract with activity schedule.
Option D: Target contract with bill of quantities.
Option E: Cost reimbursable contract.
Option F: Management contract.
Option G: Term contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Key updates from NEC3 to NEC4

A
  • Two new contracts - Design Build and Operate Contract - Alliance Contract
  • Risk register now names Early warning register
  • Employer becomes client
  • Works information becomes scope
  • Gender neutral
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When would you recommend NEC to a client?

A
  • Complex projects with clear objectives
  • Collab approach (open communication, shared goals, early problem identification)
  • Risk management and clarity
  • Typically large building or infrastructure projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why did you choose to use an Option A on the DWP expansion programme?

A
  • The government construction board recommends that public sector organisations use NEC
  • Done off a framework, collab, very little time so didn’t want BoQ
  • Client wants cost certainty so Option A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which NEC ECC poses most and least risk for employer

A

Option E - contractor reimbursed for actual loss plus fee

Option A - fixed priced contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is risk managed in NEC

A
  • Cost Risk Allowances
  • Risk registers
  • Early warnings meetings
  • Early warnings register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a compensation event

A

Unforeseen or uncontrollable event that impacts the cost or time needed to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Does NEC have relevant events and matters?

A

No, CE deals with these issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What happens if contractor notifies a CE 12 weeks after becming aware of the event

A
  • Contractor not entitled to change in prices, completion date or key date.
  • Must notify within 8 weeks of becoming aware
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is an Early Warning Notice and when would this be used?

A
  • Mechanism for both parties to identify potential problems to the project.
  • Both parties are obliged to notify the other as soon as they become aware of a matter that could affect time, cost or quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the events for a CE

A
  • Changes to WI
  • No access and use of site
  • Something not provided
  • Stop or change key date
  • Work by employer or others
  • Late reply to communication
  • Object found on site
  • Previous decision change
  • Acceptance witheld
  • Search but no defect
  • Test causes a delay
  • Unexpected conditions
  • Unexpected weather
  • Breach of contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Compensation event timeline

A
  • C to notify PM within 8 weeks of becoming aware
  • PM has one week to decide from this
  • C has 3 weeks to submit quotation from PMs request
  • PM 2 weeks to accept
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Schedule of cost components in NEC

A

Costs that can be claimed by the contractor
- People
- Equipment
- Materials
- Charges
- Manufacutre and fabrication
- Design
- Insurance and Bonds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

NEC payment timeline (under Y(UK) 2)

A
  • Assessment date
  • Due date for payment - 7 days after assessment date
  • Final date for payment - 14 days after due date for payment
  • Notice to withold payment - 7 days before final date for payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

NEC payment timeline (without Y(UK) 2)

A
  • Assessment date
  • PM certifies payment - 1 week after assessment date
  • Certified payment is made - 3 weeks or other as stated in CD after assessment date

Clause Y(UK)2 - ensure compliance with UK Housing grants, construction and Regeneration Act 1996
Without Y(UK)2 means payment date is not fixed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is retention dealt with under the NEC?

A
  • Optional retention clause (Option X16)