Systems Exam 3 - Containment Spray Flashcards

(22 cards)

1
Q

CSP Auto Starts

A

→SI Signal in conjunction with SIS on step 4 (No start on BOS)
→CS initiation signal (Hi-3 Cntmt Pressure 18.2 psig or Manual)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

LV-4754/4755 (Chem Add Tank MOVs) auto open / close on:

A

→CS initiation signal
→Close on a low level in the Chem Add Tank (~13%)
→follows normal power supply/train convention

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

-LV-4752/4753 (Chem Add Tank AOVs) auto close on:

A

→normally open
→fail open on loss of air or power
→Lo-Lo level in the Chem Add Tank (~6%).
→Power supply from opposite train

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

FV-4772-1, 4772-2 & FV-4773-1, 4773-2 (Recirc Valves) Interlocks

A

→auto close when Train related HV-4782/4783 (Sump Suction) begin to open
→auto close when Train related HV-4776/4777 (CIVs to Header) begin to open
→auto open on low discharge flow (< 1090 gpm) if the above valves are closed
→auto close on hi discharge flow (> 1210 gpm)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

HV-4776/4777 (Containment Spray HX Outlet Valves/CIVs) auto open on:

A

→CS initiation signal (2/4 Hi-3 Cntmt or Manual)
→valves are designed to slowly open (takes ~ 110 secs) to prevent pump runout while spray header fills.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

HV-4574/4575 CS HX CCW Out Valves auto open on:

A

→CS initiation signal (2/4 Hi-3 Cntmt or Manual)
→valves fully open, then throttle back to 55% of HX design flow
→if valves are already throttled to >55% design flow, they will only throttle down to 55%; will not go full open first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

TS 3.6.7 Chem Add Tank requirements

A

→NaOH concentration must be between 28% - 30% by weight
→Level must be maintained 91% - 94%.
→1-4 psig N2 overpressure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

TS 3.6.6 CS System MODE requirements

A

2 trains required in modes 1 - 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

TS 3.5.4 RWST

A

→Boron 2400-2600 ppm (restore in 8 hrs)
→Level > 95% or 473,731 gallons (restore in 1 hr)
→Temp 40 -120˚F (restore in 8 hrs; if too cold, heat by recirc through CSPs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Containment Spray is initiated by:

A

→Manual (2 of 2 H/S)
→HI-3: 18.2 psig (2 of 4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Swapover to Containment sump recirc is done when?

A

→Swapover to ctmt sump recirc is done when RWST is < 6%.
→System must be manually swapped. (EOS-1.3)
→cooling is required in recirc mode

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Recirc Valves FV-4772-1/2 & FV-4773-1/2 Auto Open / Auto Close

A

→auto open at 1090 gpm (decreasing flow)
→auto close at 1210 gpm (increasing flow)
→auto close when containment sump suction valves (isolate RWST from sump) or HX outlet valves (prevent runout) begin to open; interlock overrides flow interlocks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Containment Design Pressure and Temperature, and purpose of CT

A

→Design Pressure: 50 psig
→Design Temperature: 280°F
→Maintain containment within these limits while also removing Iodine.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Containment Spray is designed to mitigate what accidents?

A

→MSL Break inside containment
→FW Line Break inside containment
→LOCA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What chemical is used in the Containment Spray Chem Add tank and why?

A

→sodium hydroxide (NaOH) is used to raise pH in the containment sumps to a level more conducive to absorption and retention of radioactive iodine
→raising pH in the sump reduces corrosion of components in Containment, which minimizes hydrogen production
→pH raised from 4.6 to 7.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Per OPGD-3, what exception is made for Containment Spray?

A

Operators are expected to preemptively actuate ESF signals if plant conditions indicate they will auto-actuate, with the exception of Containment Spray.

17
Q

What color is the CSP 86M Phase Overcurrent light?

18
Q

If 1 Containment Spray Pump is inoperable, then the other pump in that train must be…

A

…taken to pullout due to runout concerns.

19
Q

Why are the spray risers in containment kept filled with demin water?

A

to reduce time until spray begins

20
Q

RWST Info

A

→~500,000 gallons each, one per unit
→Hi alarm >97.89%
→TS required level >95%
→Lo alarm <92.83%
→Lo-Lo alarm <33%
→Empty alarm <9%
→Low temp alarm 45° F

21
Q

Containment Spray system response to SI

A

→SI causes CSP start and run in recirc
→recirc happens before HX
→eductor flow path is open, but chem add tank MOV isolations stay closed

22
Q

Containment Spray Pump Info

A

→separate bearing coolers (SSW cooled) and seal coolers (safeguards CCW cooled)
→when one train related pump is OOS, take other pump to pullout
→if one pump in a train trips during spray, ensure other pump parameters are good and allow remaining pump to continue running
→system designed to operate with system temp up to 300° F; when system temp >150° F, CCW flow must be aligned to pump seal coolers to maintain integrity of mechanical seals
→auto-start on SIS step 4, Hi-3 containment pressure 18.2 psig; no start on BOS
→trip on sustained bus undervoltage, 86M phase overcurrent lockout (white light on handswitch)