If TIS-382 fails high…
TCV-129 diverts to the VCT and bypasses the letdown demins.
Per SOP-106 the max allowable flow(s) through BTRS demins…
is 164 gpm for one, and 300 gpm for two.
If BTRS is not isolated and the plant trips…
we could cause an inadvertent dilution of the RCS, as flow is still passing through the demins.
What is the setpoint for TE-381?
TE-381 alarms @ 150°F
What is the setpoint for TE-382? What occurs at this setpoint?
TE-382 alarms @ 155°F and diverts TCV-129 to bypass the demins.
What is the normal lineup for BTRS when in service?
Used for EOL dilution and crud burst cleanup (requires IPTE to use).
→Beds 1-2 used for crud burst
→Beds 3-5 used for dilution (100 ppm to 0 ppm)
What is the fail position for BTRS?
Fails in a boration lineup, i.e. valves 7056, 7057, 7045, and 7046 fail to place demins in boration lineup
What is the purpose of the u-7054 BTRS isolation valve?
Must be manually closed after entry into emergency procedures. Only directly addressed in FRS-0.1A(B) RESPONSE TO NUCLEAR POWER GENERATION/ATWT