ARE_Bid_Analysis_and_Process Flashcards

(25 cards)

1
Q

Why are bidding requirements stricter for publicly funded projects?

A

To ensure fairness due to the use of taxpayer funds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is required in public bidding processes?

A

Award to the lowest responsive and responsible bidder, bids opened in public, and bids recorded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does Value-Based Selection (VBS) allow?

A

Selection of contractors based on quality, schedule, or other factors besides cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Qualification-Based Selection (QBS)?

A

Private clients select contractors based on quality, speed, or subjective criteria, not just price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are RFIs during bidding?

A

Requests for Information from bidders to clarify or address missing or conflicting info in bid documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the two types of RFIs?

A

Clarification requests and substitution attempts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How should architects handle substitution RFIs?

A

Review proposed changes, evaluate impact, and issue an addendum if necessary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why must RFI responses be issued to all bidders?

A

To ensure fairness and consistency of information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of a substitution request process?

A

To provide detailed comparisons and justification for alternate products.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is value engineering?

A

Reviewing bidder-suggested alternatives to reduce cost without compromising quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What should the architect analyze in value engineering proposals?

A

Life cycle cost, durability, maintenance, and warranty vs. the basis of design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a stipulated sum bid?

A

A single all-inclusive price to perform the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When is a stipulated sum most appropriate?

A

When contract documents are complete and scope is clearly defined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a Guaranteed Maximum Price (GMP)?

A

A not-to-exceed price based on incomplete documents, including contingency for unknowns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why do GMP contracts expose contractors to risk?

A

If actual costs exceed GMP, contractor must cover the difference.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the cost-plus or time & materials method?

A

Owner pays actual costs plus a markup for overhead and profit, often used on small or renovation projects.

17
Q

What is unit pricing?

A

Contractor provides a fixed rate per unit (e.g., per SF, LF, item), useful for repetitive or undefined work.

18
Q

What is target pricing?

A

Used in DB projects, bidders propose the best solution within a set cost per unit (e.g., per SF).

19
Q

What are construction costs in a bid?

A

Direct costs to perform the work including labor, materials, insurance, mobilization, etc.

20
Q

What is a performance bond?

A

Insurance that ensures the project will be completed if the contractor defaults.

21
Q

What is contingency in a bid?

A

An amount to cover unforeseen conditions or errors, separate from owner’s contingency.

22
Q

What does overhead and profit cover?

A

Contractor’s general operating costs like salaries, rent, and administrative expenses.

23
Q

What is the bid administrator’s role?

A

Tabulate, compare, and analyze bids to recommend a contractor to the owner.

24
Q

Why is it important to analyze alternates in bids?

A

Lowest bidder may vary depending on selected alternates.

25
What is the 'bid climate'?
Economic conditions affecting labor availability, material prices, and market demand for construction.