ARE_Final_Completion Flashcards

(20 cards)

1
Q

What is Final Completion?

A

The stage when all punch list items are complete and the contractor has fulfilled all contractual obligations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Is there a Certificate of Final Completion?

A

No. Final completion is documented by the architect’s final Certificate for Payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the architect’s responsibility at Final Completion (B101 §3.6.6)?

A

Conduct final inspection and determine the date of final completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What contract section allows architects to limit inspections?

A

Section 4.2.3 of B101.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who notifies the architect when the project is ready for Final Completion?

A

The contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of limiting the number of inspections?

A

To encourage the contractor to call for inspection only when work is fully complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does the architect inspect at Final Completion?

A

Only to verify that all punch list items have been completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why is a thorough Substantial Completion inspection important?

A

To prevent delays and frustration at Final Completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is required from the contractor before final payment?

A

Final payment application, insurance certificate, warranties, consent of surety, and final lien waiver.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a lien waiver?

A

A document stating the contractor has paid all subcontractors, suppliers, and vendors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why is the lien waiver important to the owner?

A

To avoid mechanics’ liens filed by unpaid subcontractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the final change order?

A

A reconciliation of outstanding financial items like allowances, credits, or liquidated damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What happens during the final change order meeting?

A

Owner and contractor discuss and finalize financial adjustments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What happens at construction contract closeout?

A

Verify all documents are filed: field reports, G704, punch list, warranties, lien waiver, final change order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What should the owner confirm at closeout?

A

They have all documentation and contractor contact info for warranty claims.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When should the one-year follow-up meeting be scheduled?

A

At Final Completion.

17
Q

What does the architect do during their contract closeout?

A

Ensure invoices are paid, services are billed, and store project records.

18
Q

Should digital storage be prioritized during closeout?

A

Yes, but retain printed contract docs or models when appropriate.

19
Q

Why doesn’t the architect certify 100% completion?

A

To avoid liability; contractor is responsible for full completion.

20
Q

What does Final Completion trigger?

A

Final contractor payment and closeout of construction and architectural contracts.