ARE_Substantial_Completion Flashcards

(20 cards)

1
Q

What is Substantial Completion?

A

The stage when the project is sufficiently complete for the owner to occupy the space for its intended use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Does Substantial Completion mean the project is 100% complete?

A

No. There may be outstanding items, but the space must be usable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What AIA documents reference Substantial Completion?

A

B101, A101, A201.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the architect’s role at Substantial Completion (B101 §3.6.6)?

A

Conduct inspection with owner, issue Certificate of Substantial Completion, forward warranties and related docs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a punch list?

A

A list of items that must be completed or corrected before final completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who typically prepares the punch list?

A

The contractor, though the architect may do it as an additional service.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When should a project not be deemed Substantially Complete?

A

When punch list items collectively prevent the intended use of the space.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is G704?

A

AIA Certificate of Substantial Completion form.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why should consultants issue their own certificates?

A

To reduce architect liability and certify their own system completions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the difference between punch list and exceptions?

A

Punch list items will be completed; exceptions are owner-accepted deficiencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is retainage handled at Substantial Completion?

A

Portion released; remainder may be withheld to cover punch list completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does Substantial Completion trigger?

A

Release of retainage, start of warranties, turnover of utilities and site security costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What if substantial completion is delayed?

A

Contractor may owe liquidated damages if agreed upon in Article 4 of A101.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can substantial completion dates vary by portion of project?

A

Yes. This is often used in phased construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is included in the Certificate of Substantial Completion?

A

Date of substantial completion, list of exceptions, punch list, and agreements on cost turnovers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who decides if a project is Substantially Complete?

A

The architect in consultation with the owner during a site inspection.

17
Q

When are warranty periods typically initiated?

A

At Substantial Completion.

18
Q

Why is proactive contract administration important?

A

It ensures no surprises at Substantial Completion and smooths the process.

19
Q

How much retainage might be held for punch list items?

A

Usually double the value of punch list items.

20
Q

What tool can help with punch list preparation?

A

Software that documents deficiencies with photos and notes during walkthroughs.