ARE_Construction_Scheduling Flashcards
(20 cards)
Who is responsible for maintaining the construction schedule?
The contractor (per A201, Section 3.10)
What is the difference between the project schedule and the construction schedule?
Project schedule includes design and construction; construction schedule only covers the construction period.
In design-bid-build delivery, who is responsible for the schedule during the design phase?
The architect.
What changes when a CMc is used in terms of schedule responsibility?
The CMc becomes responsible for the entire project schedule.
What is Fast Track scheduling?
A method where bid packages are issued for portions of the work to compress the schedule.
Why is Fast Track scheduling riskier?
Higher risk of errors/omissions due to non-linear design and construction processes.
What must the Owner-Architect Agreement reflect if Fast Track is used?
That multiple bid packages are extra services and carry more risk.
What tool is commonly used to present a construction schedule?
Gantt chart.
How does a Gantt chart display activities?
Rows for activities, columns for time; filled cells show activity durations.
What is a task dependency in scheduling?
It defines which tasks must precede others.
What is the critical path?
The longest sequence of dependent tasks determining the project’s end date.
What is float in a schedule?
The time a task can be delayed without affecting the project’s end date.
Why must contractors update the schedule regularly?
Because the critical path changes as the project evolves.
How does the construction schedule affect site visits?
It helps the architect plan site visits within the agreed number in B101.
How does the architect use the schedule for payment applications?
To verify that progress in the pay app matches reported construction progress.
Why must the architect coordinate the submittal and construction schedules?
To ensure submittals are reviewed in time and allow for revisions.
What should the architect do if they notice the schedule slipping?
Notify the owner and help develop a strategy to get back on track.
How does the construction schedule affect submittals?
It determines the order and timing for reviews and potential revisions.
What document defines the architect’s scope for number of site visits?
AIA B101.
What should the architect do if additional site visits are required?
Amend the agreement with the owner.