ARE_Bidding_and_Delivery_Methods Flashcards

(19 cards)

1
Q

What is the primary purpose of the bidding process in construction?

A

To allow the owner to receive and compare contractor proposals for building the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is standard procedure important during bidding?

A

To ensure an apples-to-apples comparison of contractor bids.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When does bidding occur in Design-Bid-Build (DBB)?

A

After the design documents are complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is ‘Multiple Prime Contractors’ and how does it relate to DBB?

A

A variant of DBB where the owner selects more than one contractor and conducts multiple bid processes for different portions of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why might an owner choose Multiple Prime Contractors?

A

To accelerate the construction schedule by having more workers on-site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is typically required of an owner using Multiple Prime Contractors?

A

More involvement or hiring a construction manager as an advisor (CMa).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is Design-Negotiate-Build (DNB) different from DBB?

A

DNB involves proposals from one or more contractors that can be negotiated, rather than non-negotiable bids from multiple contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why might an owner prefer DNB over DBB?

A

To prequalify experienced contractors or those they’ve worked with before.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

On what type of projects is DNB usually used?

A

Privately funded projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What delivery method involves a CM brought on during design and later becomes the builder?

A

Construction Manager as Constructor (CMc) or CM at Risk (CMAR).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Is there a bidding process in CMc/CMAR?

A

No, but there may be a negotiation to arrive at a Guaranteed Maximum Price (GMP).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does ‘open book accounting’ mean in CMc?

A

All project costs are transparent to the team and savings may be split between owner and CM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does CMc incentivize cost savings?

A

Through pre-agreed savings splits, aligning CM and owner goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In Design-Build (DB), how is the contractor selected?

A

The owner negotiates early with one or more DB entities based on programmatic requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Does Design-Build (DB) involve bidding?

A

No, because the price is negotiated upfront before bidding documents exist.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the ‘Bridging’ method?

A

A variant of DB where a designer prepares schematic plans and DB entities submit bids based on them.

17
Q

How does Bridging provide more owner control?

A

The owner sees what the DB entity’s bid is based on (schematic drawings).

18
Q

Why is bidding unnecessary in Integrated Project Delivery (IPD)?

A

Because the architect, owner, and contractor form a single entity and agree on cost early on.

19
Q

What is a key feature of IPD?

A

Shared goals and collaboration among architect, contractor, and owner within a unified team.