ARE_Construction_Meetings Flashcards

(25 cards)

1
Q

What are the three key types of construction meetings?

A

Preconstruction conference, regular progress meetings, and pre-installation meetings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of the preconstruction conference?

A

To clarify roles, responsibilities, and expectations before construction begins.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who typically conducts and prepares for the preconstruction meeting?

A

The architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What documents should the architect provide before the preconstruction meeting?

A

Agenda, project authority matrix, communication protocol.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What documents should the contractor provide before the preconstruction meeting?

A

Submittal schedule, schedule of values, subcontractor/vendor list.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are key agenda items for the preconstruction meeting?

A

Submittal/RFI procedures, payment applications, SOV review, change order process, project schedule, quality control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are typical submittal and RFI review times?

A

10 business days for submittals, 3–5 business days for RFIs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of a Schedule of Values (SOV)?

A

To break down the project cost by work component for progress tracking and payments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why should the SOV be fair and balanced?

A

To prevent front-loading or back-loading which could lead to cash flow or payment issues.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is AIA G703 used for?

A

To list detailed components of the SOV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What AIA document is typically used for change orders?

A

AIA G701.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who typically prepares change orders per A201 §7.2.1?

A

The architect, unless stated otherwise in Supplementary Conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why discuss closeout requirements at the preconstruction meeting?

A

To set expectations early and prevent disputes at the end of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why should the architect compare the contractor’s schedule with their agreement?

A

To ensure their fee and staffing align with the actual project duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What should be discussed regarding project communication?

A

Lines of communication, communication protocol diagram, and centralized contacts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who speaks to subcontractors according to the protocol diagram?

A

Only the contractor.

17
Q

How often do regular progress meetings usually occur?

18
Q

What are regular progress meetings also called?

A

Owner-Architect-Contractor (OAC) meetings.

19
Q

What topics are discussed in regular progress meetings?

A

Action items, two-week look ahead, scheduling, unresolved issues.

20
Q

Who prepares meeting minutes for progress meetings?

A

The party leading the meeting.

21
Q

Why are meeting minutes important?

A

They document project progress and can be used in dispute resolution.

22
Q

What is the purpose of pre-installation meetings?

A

To coordinate installation of specific systems and confirm alignment with design intent.

23
Q

Where are pre-installation meeting requirements written?

A

In Division 01 of the specifications.

24
Q

Who should attend pre-installation meetings?

A

Contractor, relevant subcontractors, and optionally owner/architect for major systems.

25
What is one example of a system that may require a pre-installation meeting?
Flooring, due to pattern alignment and transition planning.