ARE_Testing_and_Inspections Flashcards
(20 cards)
Where are project testing and inspection requirements typically found?
In the specifications and IBC Chapter 17.
What should the architect do when creating specifications for tests?
Coordinate with consultants, senior staff, and vendors to ensure all required testing is included.
What are the three types of mock-ups?
Full-scale finished work, off-to-the-side reference mock-up, scaled-down version for approval.
What does a mock-up help verify?
Construction assembly, finish quality, material compatibility, and conformance with contract documents.
What is the slump test used for?
To measure the workability and consistency of concrete before each pour.
What is the concrete cylinder test?
Measures concrete compressive strength at intervals during the 28-day curing period.
Why is early strength testing of concrete useful?
Provides confidence that the concrete will reach its design strength before 28 days.
Why is timing important for inspections of concealed work?
Inspections must occur before work is covered (e.g., plumbing before drywall).
Who performs inspections of fire-resistant penetrations?
Typically the contractor, but the architect verifies submittal compliance with specs.
What is firestopping used for?
To maintain fire ratings of penetrated assemblies (e.g., walls with plumbing pipes).
What should the architect check in a product test report?
Applicability to project size, date within 5 years, and compliance with performance criteria.
Who pays for code-required tests per A201 §13.4?
The contractor.
Who pays for special non-code-required tests not in bid documents?
The owner.
What is the architect’s role with testing notices?
Must receive timely notice from contractor to attend if desired.
What are the architect’s responsibilities with third-party inspectors?
Assist owner in selection, confirm qualifications, coordinate schedules, and distribute results.
Who receives and distributes test reports?
Sent to contractor or owner, then forwarded to architect for review and consultant distribution.
What should happen if a test fails?
Team should evaluate, revise design if possible, or replace and retest the work.
What should the architect avoid doing if a test fails?
Directing the contractor to stop work—architect cannot direct work.
Why is contractor scheduling of tests important?
Improper sequencing can delay the project or increase costs.
What are common entities that perform testing?
Special inspectors, labs, or testing agencies with proper certifications.