ARE_Payment_Applications Flashcards

(20 cards)

1
Q

What is the architect’s primary responsibility regarding contractor’s payment applications?

A

Review and certify payment applications to confirm that billed work reflects actual progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which AIA contract section requires the architect to review and certify contractor payment applications?

A

Section 3.6.3 of B101 and Section 9.4.1 of A201.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Within how many days must the architect review and certify a payment application?

A

Within 7 days of receipt, per Section 9.4.1 of A201.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of the architect’s field reports during the payment certification process?

A

To confirm that the work completed matches what is being billed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which AIA documents are typically used for submitting payment applications?

A

G702 (Application for Payment cover sheet) and G703 (Continuation Sheet with Schedule of Values).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a schedule of values in the context of payment applications?

A

A breakdown of total contract value into specific portions of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why is the continuation sheet (G703) typically reviewed before the cover sheet (G702)?

A

Because it contains the detailed cost breakdowns that feed into the totals on G702.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is listed in Column C of G703?

A

Scheduled Value: the total allocated amount for each portion of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is listed in Column E of G703?

A

Work completed during the current pay period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is retainage, and where is it typically listed?

A

A withheld percentage to ensure project completion; listed in Column I of G703 and Line 5 of G702.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does Line 1 of G702 represent?

A

Original Contract Sum from Article 4 of A101.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does Line 3 of G702 show?

A

The current Contract Sum to Date, including net change orders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What should the architect do if Line 2 (change order value) seems incorrect?

A

Check it against the architect’s change order log.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does Line 8 of G702 show?

A

Current Payment Due: the amount requested in this application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does the architect certify when signing a pay app?

A

That the completed work matches what is represented and generally conforms to the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What should be included in the payment app certification if the amount differs from what was requested?

A

Supporting documentation explaining the change.

17
Q

Why is retainage important for the owner?

A

It protects against contractor default and incentivizes project completion.

18
Q

What document typically outlines how the schedule of values should be created?

A

Division 01 of the specifications.

19
Q

What does ‘stored material’ mean in a pay app context?

A

Materials purchased but not yet installed, often paid in advance with owner approval.

20
Q

What happens if payment is delayed due to incorrect certification?

A

Contractor may not pay subs on time, causing project delays.