AUC 149 BUCKEYE PIPELINE Flashcards

(8 cards)

0
Q

A combination wrench has both the___ &___ and is how long and what color

A

Has both the short tee wrench & long wrench in one tool. YELLOW
42” Long (3’6”)
2.3.1C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What is the length and color of the tool that is used to shut down the valves on the buckeye pipeline?

A

42” long (3’6”) YELLOW Female fitting mates with a square male fitting on the valve.

exception: Short Tee
2. 3.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

To open the latch cover to expose the valve insert the tee and rotate___–__or__.

A

1/4 turn left or right

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The 42” wrench is placed in the valve box onto of the male fitting and turned___full turns clockwise to shut off the valve.

A

42 full turns clockwise.

2.3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The only exception is the valves located on the shippers lines require ___full turn clockwise.

A

24 full turns clockwise

2.3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Department apparatus should not be brought closer than___’ to a leak.

A

600’ to a leak.
This not only removes a source of ignition, but removes personnel from any vapor cloud present.
6.5.7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

T/F

When requesting train traffic stopped the IC must request both power removal and trains stopped. Some trains are diesel.

A

TRUE

6.6.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

And in addition must position “flag persons” at least___’ on each side of the incident.

A

At least 1000’ in each direction.

6.6.3