1
Q

What will you need to do to test with no gas pressure

A

You will need gas pressure to the low gas pressure switch, or you will need to jump it out to complete some of the tests.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Confirm what on the flame safeguard

A

model number is correct and meets all code requirements for the application.
is a connected dedicated ground wire installed on the subbase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which tests verify that the subbase is wired correctly, and the external controllers, limits, interlocks, actuators, valves, transformers, motors and other devices are operating properly.

A

static checkout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

To perform the Static Checkout, you will need

A

multi-meter and a pair of 14 AWG jumpers with alligator clips at each end.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a Pilot Turndown Test

A

Make sure the pilot lights the burner at min pilot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the minimum and maximum flame signals

A

Max flame signal 5 VDC
Min flame signal 1.25 VDC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What should be the flame failure response time

A

Less than 1 second

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Dynamic Self Check

A

When it interrupts the flame sense with a self-check shutter that is 0.4 sec closed / 3.6 sec open

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In cases where no Canadian-recognized standard or ORD exists the client must contact

A

an SCC-accredited inspection body

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

performing regulated work or operating a regulated product without the required permit is prohibited. Offenders may face fines up what and jail time up to what

A

fines up to $100,000 and/or imprisonment for up to 18 months for individuals, or fines up to $200,000 for corporations, with additional penalties for ongoing offences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

any direct-fired non-recirculating type make-up heater;
a conversion burner, except if it is to be installed in a single family dwelling and has an input of 120 kW or less;
a commercial or industrial conversion burner;
any direct fired equipment;
a forced draft appliance over 409,600 Btuh.
need what

A

Commissioning approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The permit holder must request the assessment at least how many hours prior to the expected commissioning time

A

48

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Appliances found operating contrary to these requirements may be ordered removed from service by who

A

Gas Safety Officer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Upon arrival at a worksite, it is crucial to perform what

A

Job Hazard Assessment to identify potential risks and hazards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which report includes combustion information and flue gas analysis results.

A

detailed appliance start-up report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Where do you send the detailed appliance start-up report

A

Technical Safety BC

17
Q

Printed results of the combustion settings are typically left where

A

with the appliance

18
Q

Changes made are recorded as “as built” and the diagrams are left where

A

with the appliance

19
Q

It is common to have the sites responsible party fill out what

A

a pre-commission checklist.

20
Q

What is probably the most common challenge for the commissioning technician.

A

Adequate load