Contract Administration Flashcards

(71 cards)

1
Q

What details should be included in an employer’s change instruction?

A

Date
Reference number
project details
contractor and employer details
contract details
change detail including drawings and specification as required
signature
distribution list
Quantity/rate/costs if agreed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Examples of reasons for instructions?

A

Changes
Postponement of work
Expenditure of provisional sums
Opening up works
Correction of work not in accordance with the contract
Dealing with antiquities, contaminated materials and unexploded ordinance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Under a JCT design and build, does it always have to be monthly payments?

A

Gross Valuation - Alternative A is for stage payments

Gross Valuation - Alternative B is for periodic payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name 3 Relevant Matters.

A
  • Instructions/variations
  • Impediment, prevention or default by the Employer
  • Postponement of works by employer
  • Instruction of provisional sums specified in the ERs
  • Instructions for opening up works, unless works are found to not be in accordance with the contract.
  • Epidemic (as long as stated as applying in the contract particulars)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name 3 Relevant Events.

A

Exceptionally adverse weather conditions
Deferment of possession
statutory body works
force majeure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Contractors Design Portion?

A

It is a specific element of a contract that outlines specific elements a contractor is obliged not to only construct but also design

This should be clearly defined within the contract and subsequently agreed by the selected contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an Extension of Time?

A

A formal agreement to extend the date by which a project is to be completed by.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is required for an Extension of Time to be awarded?

A

Relevant event

Expected delay to the completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Name some examples of a relevant event?

A

Force Majeure
Deferment of Possession
Employer instructions
Adverse weather conditions
Strikes / industrial action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a Force Majure

A

Relevant Event that frees both parties from liability or obligation when an extraordinary event or circumstance beyond the control of the parties prevents one or both parties from fulfilling their obligations under the contract.

Such as a
- war
- strike
- riot
- crime
- pandemic
- or an event described as an act of God (like flooding, earthquake, or volcanic eruption),

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Process of an Extension of Time?

A

Contractor to Notify Employer as soon as reasonably apparent of potential delay to the completion to the completion date
Formal EoT request to be issued by contractor to the CA/EA
This should identify the Relevant Events that have occurred to result the delay
EA/CA to review and provide a formal response / decision to the request within 8 weeks
This has been updated to 8 weeks within the JCT 2024 contract update, previously 12 weeks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the insurance of the works options under a JCT contract?

What do they protect against?

A

Insurances of the works options under a JCT contract are specific insurances that protect against risks such as fire, theft or damage.

There are three options A, B & C with each determining who has responsibility for the insurance and the extent to which it covers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Insurance Option A?

A

Option A - All Risk insurance by Contractor for new buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What Insurance Option B?

A

Option B - All Risk insurance by the Employer for new buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What Insurance Option C?

A

Option C - Insurance by the Employer for existing structures (specified perils only) and works in or extensions to them (all risks)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the specified perils?

A

They are defined in the contract definitions which refers to clause 6.8.

Includes things like fire, lightning, explosion, storm, flood, earthquake.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is All Risks Insurance?

A

Insurance which provides cover against
- any physical loss
- or damage
to work executed and site materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What types of insurance are required under JCT?

Briefly describe each

A

Employers’ Liability Insurance:
- This covers the employer’s liability for injuries to their employees arising from their employment on the project.

Public Liability Insurance:
- This covers liability for personal injury or property damage to third parties.

Professional Indemnity Insurance: (only if there is design)
- This covers liability for professional negligence, particularly for design consultants like architects and engineers.

Liability of employer - Non negligent insurance (optional)
- Contractor takes out joint names to cover against injury or damage to the works, excluding things covered under other insurances. (Often referred to as non-negligent insurance)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

For what reasons could an employer terminate the contract?

A

Contractor suspends works without reasonable cause
Contractor fails to proceed regularly or diligently with their contract obligations
Contractor refuses to remove non-compliant work
Contractor assigns the contract to another party or sub contracts the works or design of the works.
Contractor does not comply with CDM regulations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

For what reasons could a contractor terminate the contract?

A

(8.9.1) Employer does not pay by final date for payment
Employer assigns the contract to another party (7.1)
Employer does not comply with CDM regulations
Employer interferes with issuing of any certificate due under the contract (intermediate only)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is a Joint Names Policy?

A

A policy taken out that covers both the client and the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the benefit of taking out joint names insurance?

A

Both parties can claim

Both parties can be paid directly.

They do not need to wait for the other party to claim or pay them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Which of the three insurance options are joint names

A

All three of them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is Sectional Completion?

A

A provision within a contract that allows for different sections of work

These sections should be clearly defined within the contract documents

The dates for possession & completion should be clearly defined.

They should have their own Liquidated Damages rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Practical Completion at Sectional Completion
The process of sectional completion is exactly the same as practical completion
26
Define Practical Completion?
There is no set definition in the JCT contracts. Practical completion, in terms of construction and property, refers to the stage when a building project is completed except for minor defects that can be put right without causing significant interruption to occupants RICS Black Book on Defining Completion of Construction Works
27
What is an Interim Valuation and what is the timeline? | In terms of JCT Design and Build
- Interim Valuation date specified under the contract (This contract was month or the nearest business day after possession of the site.) - Contractor submits application on IVD - Due date is 7 days after the IVD or the contractor's application, whichever happens last. - The EA has no later than 5 days after due date to submit their Payment Notice or else the application becomes due for payment. - Payment date is typically 14 days after the due date - Employer must issue a payless notice no later than 5 days before the final date for payment if they wish to do so
28
What is the difference between and EA & CA?
EA acts on behalf of the Client as if the EA was the employer. Impartial role. Design and Build contract CA administers the contract for the employer. Impartial role. Only exists at the point the contract is entered into. All other contracts, except D&B. EA on D&B contract only
29
What is an Employers Agent?
The EA is a representative who administers the contract on the employers behalf only within a D&B Must act with honesty and integrity
30
What is a Contract Administrator?
Tasked with managing all aspects of a construction contract throughout Must act with honesty and integrity
31
What is the default D&B retention %? | What is the proportion of the first retention release?
3%, first retention release is always half of the specified amount.
32
What is default JCT Intermediate retention %? | Pre and post PC
Valuation paid at 95% before PC, 97.5% after PC. Either % can be changed independantly of the other.
33
What are the roles and responsibilities of the contract administrator?
The JCT Contract Administrator manages the construction contract on behalf of the employer. Their key responsibilities include issuing instructions, certifying payments and completion, managing variations, and assessing delays. They act impartially when administering the contract and ensure compliance with its terms throughout the project.
34
Explain the change procedures within JCT contracts?
Identify change Change is instructed Cost implication? Potential EoT?
35
What are the Change valuation options in D&B?
Consistent with values of work in CSA CSA rates pro-ratad/adjusted if required Where there is no similar work in CSA, a fair assessment is made. Last resort is to use dayworks
36
How do you calculate Dayworks?
The prime cost of works together with OHP added at the agreed rate or at the all inclusive labour rates agreed D&B Clause 5.5
37
What do you not include within a contractors valuation?
VAT Works not yet completed Materials that are not protected from weather or are on site prematurely Works that are not completed in accordance with the contract, including unagreed variations Retention to be withheld
38
Can offsite materials be included in a valuation?
They can be included if they are named as Listed Items in the contract documents and the following conditions are met: -items in accordance with contract -contractor has provided employer with proof of vesting to CONTRACTOR and insurance of the items -Items must be set aside and clearly labelled -Bond in place if required in contract particulars
39
What items are not subject to retention in valuations?
Loss and Expense Insurances suspension costs Fluctuations
40
What is practical completion?
Practical Completion signifies the project is complete except for any minor defect that will not impact the cause significant inconvenience to the occupier. It marks the point when the contractors obligation to insure the works and liability for liquidated damages and the rectification period begins.
41
What happens at Practical Completion?
PC triggers the following: Release of retention (half) Marks the beginning of the rectification period Site possession transferred to the client Client must ensure they have the correct level of insurance Contractors obligation to pay out any LDs ends
42
What is a Final Account Statement include?
The date Contract date Contract value Variation costs Agreement conditions Signatures
43
What should be included within a completion certificate?
Employers address Employers agent contractors address contract dates date of practical completion date of rectification period Snagging items description of works
44
What is the deferment of possession?
Relates to the date the contractor can access a site to start construction Deferment means that this date can be postponed
45
What is the default max period of deferment of possession?
The employer can defer possession of the site for 6 weeks
46
What is an extension of time? Benefit to the contractor?
Extension of time under a JCT contract is a formal notice that extends the contract period and the completion date without the contractor having to pay Liquidated Damages Usually as a result of unforeseen circumstances or change of scope from the client (relevant event)
47
What are typical contract documents?
Schedule of main contract documentation Legal documentation (JCT Contract) Pricing document (CSA) Preliminaries and General Conditions Employers Requirements (Design Spec / Surveys)
48
Elleray Hall - Explain the potential consequences of not issuing a payment notice for an interim valuation.
Under D&B, if a Payment Notice is not issued within 5 days of the due date, the Employer must pay the contractor the sum claimed in their interim application, subject to any pay less notices issued by the Employer.
49
Gallery Court - What documentation was issued in the extension of time process? ( Documents from contractor and EA )
Gallery Court was D&B. The contractor gave notice that the works would be delayed as soon as it became reasonably apparent. They provided explanation of the delay reasons as well as showing on a programme how the temporary postponement of works had affected the critical path. The EA reviewed the claim for extension of time and awarded an Extension of Time for 4 weeks.
50
Gallery Court - What was the reason for the EoT being awarded and how long was awarded?
Employer made a number of changes to the works required. 4 weeks were awarded.
51
What is a Payment Notice? | JCT D&B
A written notice which sets out the amount the employer considers due at the due date for payment and the basis on which it has been calculated.
52
Who are the relevant parties involves with payment notices?
Employer Contractor EA / CA
53
What is a pay less notice?
In the event the employer intends to pay less than the amount the contractor has applied for / the payment notice amount
54
Name an example when an employer may use a pay less notice?
Defect in the work or the standard was not as per the contract documents Or Payment Notice not issued in time and the contractor’s application becomes due to be paid
55
Elleray Hall - What did you include in the change control logs that you produced?
Change description Date Status Cost and time estimate Action Decision deadline
56
Elleray Hall - What are the contract requirements that an EA Instruction must comply with? What specific clarification can contractor ask under the contract?
Instructed by the EA Issued in writing Clear, precise and unambiguous Comply with contract and not breach it Contractor can ask which contract provision empowers EA to issue the instruction.
57
Elleray Hall - What does the contract say are amounts due at interim valuations? Which are subject to retention and which aren't?
Subject to retention: completed works (including design) Site materials Listed items NOT subject to retention: Insurance Loss and Expense Fluctuations provision
58
What are the potential costs that can be included in a liquidated damages rate?
It could include loss of profit, storage costs, loss of rent, professional fees Local authorities can include their staff costs
59
You said the opportunity to claim Liquidated Damages would be lost if too much money was expended against the contract. What did you mean?
Whilst the contract does allow for the contractor to pay back liquidated damages, it would be significantly harder to get them to do this than if the monies were deducted from valuation payments.
60
What alternatives are there to retention?
Retention bond - A retention bond is a form of insurance-backed guarantee. Employer receives a payment in event that contractor doesn't make good defects.
61
What would happen if the Payment Notice was not issued in time? | Or a Valuation Certificate in ICD terms?
D&B - The amount claimed by the contractor in their application becomes due. Intermediate - If a Valuation Cert was not issued, the contractor's application becomes a Payment Notice (or they can issue a Payment Notice if no application was made) which is then due.
62
With regards to your contract administration, just say your role had finished, everyone was happy and the completion of the project had been made, how long would you hold this file for?
It would depend on the liability of the project, underhand the liability is for 6 years from PC whilst deed is 12 years from PC. I asked my company and they actually hold information for past projects for 30 years and future projects for 15 years as a requirement under Building Safety Act 2022.
63
What is the limitation period for claims under a deed versus a contract under hand?
Deed: 12 years Under hand (a standard/simple contract): 6 years
64
What was the LD's rate for Leopold?
£2,500/week or part there of
65
What was the LD's rate for Gallery Court?
£7,500.00 per week or part thereof, capped to a maximum value of £150,000.00
66
What was the LD's rate for Highgate West?
The LD's varied for each section depending on the number of bedrooms affected by the works. The lowest ward was £2,000 per week whilst the highest was £8,000 per week.
67
What was the LD's rate for Elleray Hall?
Section 1 - £12,000 per week Section 2 - £6,000 per week
68
Name some forms of contracts under the JCT suite of contracts?
Standard Intermediate Minor Works Design and Build
69
You mentioned you produced a change control log, what was the process behind that ? What was included in the change log?
I discussed with the EA whether the items were a change or just design development. Once confirmed as a change I added the change information to the change log to be issued to the client for approval. A change control log will include: Date Description Reason Time/Cost impact Status
70
What is section 278?
A section 278 agreement (or s278) is a section of the Highways Act 1980 that allows developers to enter into a legal agreement with the council (in their capacity as the Highway Authority) to make permanent alterations or improvements to a public highway, as part of a planning approval.
71
What is a section 106?
Section 106 (S106) Agreements are legal agreements made between Local Authorities and developers. The agreements are linked to planning permissions and can also be known as planning obligations. S106 agreements are drafted when it is considered that a development will have a significant impact on the local area that cannot be moderated by means of conditions attached to a planning decision. For example, a new residential development can place extra pressure on the social, physical, and economic infrastructure which already exists in a certain area. The most common obligations include:- Public open space Affordable housing Education Highways Town centre improvements Health Recreation disturbance avoidance and mitigation strategy (RAMS)