Contract Administration Flashcards
(71 cards)
What details should be included in an employer’s change instruction?
Date
Reference number
project details
contractor and employer details
contract details
change detail including drawings and specification as required
signature
distribution list
Quantity/rate/costs if agreed
Examples of reasons for instructions?
Changes
Postponement of work
Expenditure of provisional sums
Opening up works
Correction of work not in accordance with the contract
Dealing with antiquities, contaminated materials and unexploded ordinance
Under a JCT design and build, does it always have to be monthly payments?
Gross Valuation - Alternative A is for stage payments
Gross Valuation - Alternative B is for periodic payments
Name 3 Relevant Matters.
- Instructions/variations
- Impediment, prevention or default by the Employer
- Postponement of works by employer
- Instruction of provisional sums specified in the ERs
- Instructions for opening up works, unless works are found to not be in accordance with the contract.
- Epidemic (as long as stated as applying in the contract particulars)
Name 3 Relevant Events.
Exceptionally adverse weather conditions
Deferment of possession
statutory body works
force majeure
What is a Contractors Design Portion?
It is a specific element of a contract that outlines specific elements a contractor is obliged not to only construct but also design
This should be clearly defined within the contract and subsequently agreed by the selected contractor.
What is an Extension of Time?
A formal agreement to extend the date by which a project is to be completed by.
What is required for an Extension of Time to be awarded?
Relevant event
Expected delay to the completion date
Name some examples of a relevant event?
Force Majeure
Deferment of Possession
Employer instructions
Adverse weather conditions
Strikes / industrial action
What is a Force Majure
Relevant Event that frees both parties from liability or obligation when an extraordinary event or circumstance beyond the control of the parties prevents one or both parties from fulfilling their obligations under the contract.
Such as a
- war
- strike
- riot
- crime
- pandemic
- or an event described as an act of God (like flooding, earthquake, or volcanic eruption),
Process of an Extension of Time?
Contractor to Notify Employer as soon as reasonably apparent of potential delay to the completion to the completion date
Formal EoT request to be issued by contractor to the CA/EA
This should identify the Relevant Events that have occurred to result the delay
EA/CA to review and provide a formal response / decision to the request within 8 weeks
This has been updated to 8 weeks within the JCT 2024 contract update, previously 12 weeks.
What are the insurance of the works options under a JCT contract?
What do they protect against?
Insurances of the works options under a JCT contract are specific insurances that protect against risks such as fire, theft or damage.
There are three options A, B & C with each determining who has responsibility for the insurance and the extent to which it covers.
What is Insurance Option A?
Option A - All Risk insurance by Contractor for new buildings
What Insurance Option B?
Option B - All Risk insurance by the Employer for new buildings
What Insurance Option C?
Option C - Insurance by the Employer for existing structures (specified perils only) and works in or extensions to them (all risks)
What are the specified perils?
They are defined in the contract definitions which refers to clause 6.8.
Includes things like fire, lightning, explosion, storm, flood, earthquake.
What is All Risks Insurance?
Insurance which provides cover against
- any physical loss
- or damage
to work executed and site materials
What types of insurance are required under JCT?
Briefly describe each
Employers’ Liability Insurance:
- This covers the employer’s liability for injuries to their employees arising from their employment on the project.
Public Liability Insurance:
- This covers liability for personal injury or property damage to third parties.
Professional Indemnity Insurance: (only if there is design)
- This covers liability for professional negligence, particularly for design consultants like architects and engineers.
Liability of employer - Non negligent insurance (optional)
- Contractor takes out joint names to cover against injury or damage to the works, excluding things covered under other insurances. (Often referred to as non-negligent insurance)
For what reasons could an employer terminate the contract?
Contractor suspends works without reasonable cause
Contractor fails to proceed regularly or diligently with their contract obligations
Contractor refuses to remove non-compliant work
Contractor assigns the contract to another party or sub contracts the works or design of the works.
Contractor does not comply with CDM regulations
For what reasons could a contractor terminate the contract?
(8.9.1) Employer does not pay by final date for payment
Employer assigns the contract to another party (7.1)
Employer does not comply with CDM regulations
Employer interferes with issuing of any certificate due under the contract (intermediate only)
What is a Joint Names Policy?
A policy taken out that covers both the client and the contractor
What is the benefit of taking out joint names insurance?
Both parties can claim
Both parties can be paid directly.
They do not need to wait for the other party to claim or pay them.
Which of the three insurance options are joint names
All three of them.
What is Sectional Completion?
A provision within a contract that allows for different sections of work
These sections should be clearly defined within the contract documents
The dates for possession & completion should be clearly defined.
They should have their own Liquidated Damages rate