Quantification and Costing Flashcards
(47 cards)
What are the benefits of using a Bill of Quantities for construction work?
A bill of quantities:
- provides an accurate assessment of required materials, labour and equipment, allowing a robust basis of cost estimation
- ensures tenders are directly comparable
- allows for easy assessment of change
Which non-works costs does the NRM provide guidance for?
Preliminaries
overheads and profit
risk allowances
inflation.
When would you use NRM 1?
Order of cost estimating and cost planning for capital building works
When would you use NRM 2?
Detailed measurement for building works
When would you use NRM 3?
Order of cost estimating and cost planning for building maintenance works
What stages would you undertake an order of cost estimate?
Stages 0 and 1, Stage 2 would be a cost plan.
What is the difference between Bill of Quantities, Contract Sum Analysis & Activity Schedules?
BoQs - To provide a detailed, measurable list of all the work required for a project, used for tendering, cost control, and valuing variations.
CSA - To provide a breakdown of the contractor’s tender price, allowing for analysis and comparison of tenders, and to form a basis for payment calculations. Particularly useful for D&B projects where full design is not available at tender.
Activity Schedule - NEC Term - To list project activities as shown on the programme with a lump-sum price for each, simplifying the administration of the interim payment process
What are the methods for valuing a variation?
contract rates for works the same
Pro rata rates for similar works
Fair valuation where there is no similar work in contract sum (built up from labour and materials, or a quote/benchmark/price book)
dayworks as a last resort:
- Prime cost plus agreed OHP
- Agreed all in labour rates
What do you not include within a contractors valuation?
VAT
Works not yet completed
Materials that are not protected from weather or are on site prematurely
Works that are not completed in accordance with the contract, including unagreed variations
Retention to be with held
What items are not subject to retention in valuations?
Loss and Expense
Insurance premiums
fluctuation provisions
contractor suspension costs as a result of non payment by employer
Artizan Court - Give me a take off list for the decking and soffit works.
Decking area (decking material, underlay, waterproofing)
Railings measure (balustrade, handrail)
Edge measure (edge treatment, cladding)
Soffit area (soffit materials)
· Artizan Court - You mentioned an estimation of additional decking that was lower than the contractors. Why was yours lower?
I made my assessment based on rates and benchmarks available to me at the time. They did not provide such back up so it was not clear why mine was lower.
· Artizan Court - Did you challenge the high decking cost?
I did challenge the high cost but the contractor was adamant they would not complete the works at a lower cost so I had to inform the employer that it would be more expensive to bring in another contractor.
The change works were significant in quantity, cost and scope of works which meant the contractor would have had grounds for reasonable objection to the instruction.
Artizan Court - What additional costs would be required if a new contractor was brought in to carry out the decking works.
Site preliminaries (cabins and welfare etc.)
Insurances
scaffolding
tendering costs
Elleray Hall - What are the risks of using rates taken from historical data?
Outdated costs with different conditions due to changes in the economy, laws and regulations
Over reliance on historical data could lead to inaccurate predications about the future
Don’t know original origin of the rates
Indices adjustments are a forecast only
Elleray Hall - How did you establish which tenderer to recommend? Explain the tasks and actions you carried out to provide your recommendation.
Tender Report:
- Arithmetical check
- Reviewed the tenders and added allowances for any missing costs
- Reviewed preliminaries
- Reviewed OHP
- Reviewed provisional sums
- Produced a quantitive score which was combined with the EA’s qualitive score to provide the recommendation
What are the options for dealing with arithmetical errors in tenders.
The JCT Tendering practice note 2017 dictates the course of action if any arithmetical errors exist. The method of dealing with errors should have been outlined in the tender documents.
The options are either to allow the contractors either to:
Option 1: stand by or withdraw
Option 2: stand by their price or amending it to correct genuine errors.
Elleray Hall - What were the headings in your tender report?
Tender process and methodology
Arithmetical checks
Adjusted tender sums
preliminaries
professional fees
overheads and profit
tender scoring
value engineering
Elleray Hall - What were the tender report next steps required to agree a contract sum?
Client to confirm acceptance our contractor recommendation
Inform tenderers of the result
Firm up remaining items such as tender adjustments and provisional sums
Agree contract sum
Elleray Hall - Why did you need to negotiate costs following the tender process?
There were some provisional sums entered in the contractors tender return which we wanted to firm up.
Leopold Buildings - Advise me what you learnt from carrying out the assessment of loss and expense?
I learnt that:
-L&E must be for direct costs relating to delays, not indirect costs
- the JCT contracts include two conditions precedent for L&E such as the contractor making an application promptly
and that the contractor is required on request to submit supporting information for the QS to ascertain loss and expense
Leopold Buildings - What was the Relevant Event stated in the Extension of Time?
There was 2
Any impediment, prevention or default by the Employer - the employers residents were not allowing access to the apartments at the required times so this was viewed by the CA as prevention by the Employer.
And statutory body works
Leopold Buildings - What were the heads of claims included in the Loss and Expense claim?
Potential Loss and Expense heads of claim must be direct loss and expense and can include:
-preliminaries prolongation costs
-preliminaries thickening costs
-loss of profit
-overheads
-acceleration costs
Name 3 Relevant Events
- Changes/Variations
- Postponement of works
- Expenditure of prov sums included in ER’s
- Impediment, prevention or default of employer
- Exceptionally adverse weather conditions
- Deferment of possession
- statutory body works
- Specified peril
- force majeure
- epidemic