Contract Practice Flashcards
(63 cards)
Could you explain what the roles of the client, contractor and consultants involve under traditional JCT contracts?
Under the JCT contracts:
- the client is responsible for expressing the project requirements, making payment to the contractor, employing consultants
- the contractor is responsible for developing the design, managing and executing construction, application for payment
- consultants (like architects, quantity surveyors, principal designer etc.) provide professional services and advice.
Which consultants are specified in the D&B 2024 contract?
EA
PD and PC for CDM
PD and PC for Building Regs
Which consultants are specified in the Intermediate contract?
Architect/CA
QS
PD and PC for CDM
PD and PC for Building Regs
What is the role of the Quantity Surveyor in the Intermediate Contract?
Valuation assessments
Issuing pay less notices
L&E assessments
Final account
Variation assessments
What are the changes from JCT 2016 to JCT 2024
Gender neutral language.
Notices can now be served by email.
New Article 7 requires identification of the Principal Designer and Principal Contractor
Epidemic is added as a Relevant Event and an optional Relevant Matter
Changes in law now seen as a Relevant Event and optional Relevant matter
Asbestos, contaminated materials and uxo’s can now be claimed as RE and RM.
Delays - Employer has 14 days to notify contractor of further information required to reach a decision and now have 8 weeks to provide a decision, not 12.
LD’s can’t be claimed if contract terminated
Fluctuations text moved online.
Notification and negotiation provisions are now integrated, not supplemental.
Sustainability provisions are now integrated, not supplemental.
PD and PC now required for Building Regulations as well as CDM regs (previously included)
Could you explain how JCT 2024 contracts has or will affect the industry, if at all?
Digital Integration – Incorporates provisions for electronic communications, allowing critical notices to be served via email to specified addresses.
Enhanced Building Safety – Article 7 addresses the appointment of duty holders under the Building Safety Act 2022, ensuring compliance with new safety regulations.
Any future epidemics delays will be easier to deal with in terms of time and money due to a new Relevant Event and optional Relevant Matter.
What do you believe are the key benefits of using JCT contracts in the construction industry?
clarity of responsibilities,
certainty of obligations and rights, and risk allocation between parties.
provide a regulatory framework that is thorough and understood across the industry.
What are the basic requirements to make a contract binding in the construction industry?
Offer
Acceptance
Consideration
Intent to create legal relations
Capacity
Legality
Could you provide an example of how your understanding of these contracts has been put to practical use in a project?
When reviewing a claim for Loss & Expense:
Review the reason for the delay and whether that is a relevant matter
Review the contractor’s loss and expense claim to, checking it was submitted in accordance with contractual timescales
Request additional cost back up where required
Agree the final cost, to avoid disputes
Can you provide an outline of the JCT Design and Build contract?
a contract where the contractor is responsible not only for the construction but also the design of the project.
It has a single point of responsibility, simplifying the client’s management of the contract.
Can you provide an outline of the JCT Intermediate contract with contractors design?
the client takes on design change risks except for items specifically listed in the contractor’s design portion.
Simple works involving all the recognised trades and skills of the industry, where fairly detailed contract provisions are needed, but without complex building service installations or other specialist work
Potentially for projects between £250k and £1.5million
When would a JCT Design & Build be suitable?
D&B is suitable when a project is simple in nature and the client wants to remove risk.
can vary in scale, but the Design and Build Contract is generally suitable where detailed provisions are needed.
When might a JCT Intermediate contract be suitable?
Projects involving all the recognised trades and skills of the industry, where fairly detailed contract provisions are needed, but without complex building service installations or other specialist work
Typically suitable for projects that range in value from approximately £250,000 to £1.5 million. Please note that these prescribed values are only indicative and can change depending upon various factors like complexities involved, project duration and expertise required.
Explain contractor’s design within the intermediate contract?
The contractor is responsible for developing the design for ‘discrete parts’ listed in the Contractors Design Portion.
What strategies did you use to handle complications that arose due to the wards in the mental health centre being live during its reconfiguration?
Contract sections were used to split up the wards
contract sections were phased to allow for ward relocation while minimizing disruption.
Highgate West - Can you describe your method for splitting the contract into different sections, and how this benefited the progress of Highgate West?
The contract sections were split by each ward/area following discussions with the EA and Employer.
I then sought information required for each sections such as possession date, completion date, liquidated damages rate, rectification period.
Sections allowed the wards not in contractor’s possession to stay live until they were handed over to the contractor.
In relation to the Leopold Buildings project, can you detail how you carried out and managed monthly interim valuations?
Leopold was under an Intermediate contract, so I would carry out the valuation in line with the due date, with or without contractor application.
I visited site to for a physical verification of work completion as well as reviewing clerk of work reports to determine the accurate value of works completed.
I then discussed my assessment with the contractor to maintain a good working relationship before issuing to the CA for them to issue their Interim Certificate.
Could you elaborate on the process you followed when assessing variation on Leopold, particularly concerning gas pipework rerouting?
I studied the contract drawings, identifying the scope of the variation
I communicated with the contractor to get an estimated cost and time impact if applicable before making my assessment.
In the case of the gas pipework rerouting, I analysed the technical necessities and reviewed the contractors costs against benchmark figures that we had on similar projects.
What did you mean by the Contractor’s requirements under the contract?
I meant the works they are required to do under the contract.
How did the contractor’s contract work requirements affect your decision when determining the relevance of the claimed variation costs?
I would review the claimed variation and compare the works with the contract works to check if they were a valid variation.
Can you share your experience in handling Extensions of Time issued by the Contract Administrator and how did this impact Loss and Expense claims?
Extensions of Time changes the way the preliminaries are assessed in interim valuations. Preliminaries should be paused during an EoT period.
I would review the EoT Relevant Event to see if there was an equivalent Relevant Matter to allow the contractor to claim L&E.
How did your understanding of JCT contractual provisions contribute to the final account discussions with the contractor in the Leopold Buildings project?
My understanding of the contract final account timelines
I reviewed the EoT’s awarded and which of these enabled the contractor to claim L&E for those periods
I reviewed the instructions issued to determine their value
All of the above enabled me to negotiate and reach a satisfactory final account conclusion for all parties.
What process and considerations did you have when dealing with matters such as liquidated damages, retention and practical completion?
I considered the contract dates, as well as if the EA/CA had issued an extension of time.
I ensured to consider and have a good understanding of the contractual matters including timescales and responsibilities.
I would ensure good communication with all parties involved.
On Leopold, how did you determine if liquidated damages were due and how did you value them?
I reviewed the time period between the revised completion date and practical completion and then applied the contract liquidated damages rate to this period. I informed the client of the amount of LD’s that were due to them.