Contract Practice Flashcards

(63 cards)

1
Q

Could you explain what the roles of the client, contractor and consultants involve under traditional JCT contracts?

A

Under the JCT contracts:
- the client is responsible for expressing the project requirements, making payment to the contractor, employing consultants

  • the contractor is responsible for developing the design, managing and executing construction, application for payment
  • consultants (like architects, quantity surveyors, principal designer etc.) provide professional services and advice.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which consultants are specified in the D&B 2024 contract?

A

EA
PD and PC for CDM
PD and PC for Building Regs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which consultants are specified in the Intermediate contract?

A

Architect/CA
QS
PD and PC for CDM
PD and PC for Building Regs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the role of the Quantity Surveyor in the Intermediate Contract?

A

Valuation assessments
Issuing pay less notices
L&E assessments
Final account
Variation assessments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the changes from JCT 2016 to JCT 2024

A

Gender neutral language.
Notices can now be served by email.
New Article 7 requires identification of the Principal Designer and Principal Contractor
Epidemic is added as a Relevant Event and an optional Relevant Matter
Changes in law now seen as a Relevant Event and optional Relevant matter
Asbestos, contaminated materials and uxo’s can now be claimed as RE and RM.
Delays - Employer has 14 days to notify contractor of further information required to reach a decision and now have 8 weeks to provide a decision, not 12.
LD’s can’t be claimed if contract terminated
Fluctuations text moved online.
Notification and negotiation provisions are now integrated, not supplemental.
Sustainability provisions are now integrated, not supplemental.
PD and PC now required for Building Regulations as well as CDM regs (previously included)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Could you explain how JCT 2024 contracts has or will affect the industry, if at all?

A

Digital Integration – Incorporates provisions for electronic communications, allowing critical notices to be served via email to specified addresses.

Enhanced Building Safety – Article 7 addresses the appointment of duty holders under the Building Safety Act 2022, ensuring compliance with new safety regulations.

Any future epidemics delays will be easier to deal with in terms of time and money due to a new Relevant Event and optional Relevant Matter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What do you believe are the key benefits of using JCT contracts in the construction industry?

A

clarity of responsibilities,

certainty of obligations and rights, and risk allocation between parties.

provide a regulatory framework that is thorough and understood across the industry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the basic requirements to make a contract binding in the construction industry?

A

Offer
Acceptance
Consideration

Intent to create legal relations
Capacity
Legality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Could you provide an example of how your understanding of these contracts has been put to practical use in a project?

A

When reviewing a claim for Loss & Expense:
Review the reason for the delay and whether that is a relevant matter
Review the contractor’s loss and expense claim to, checking it was submitted in accordance with contractual timescales
Request additional cost back up where required
Agree the final cost, to avoid disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can you provide an outline of the JCT Design and Build contract?

A

a contract where the contractor is responsible not only for the construction but also the design of the project.

It has a single point of responsibility, simplifying the client’s management of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Can you provide an outline of the JCT Intermediate contract with contractors design?

A

the client takes on design change risks except for items specifically listed in the contractor’s design portion.

Simple works involving all the recognised trades and skills of the industry, where fairly detailed contract provisions are needed, but without complex building service installations or other specialist work

Potentially for projects between £250k and £1.5million

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When would a JCT Design & Build be suitable?

A

D&B is suitable when a project is simple in nature and the client wants to remove risk.

can vary in scale, but the Design and Build Contract is generally suitable where detailed provisions are needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When might a JCT Intermediate contract be suitable?

A

Projects involving all the recognised trades and skills of the industry, where fairly detailed contract provisions are needed, but without complex building service installations or other specialist work

Typically suitable for projects that range in value from approximately £250,000 to £1.5 million. Please note that these prescribed values are only indicative and can change depending upon various factors like complexities involved, project duration and expertise required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Explain contractor’s design within the intermediate contract?

A

The contractor is responsible for developing the design for ‘discrete parts’ listed in the Contractors Design Portion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What strategies did you use to handle complications that arose due to the wards in the mental health centre being live during its reconfiguration?

A

Contract sections were used to split up the wards

contract sections were phased to allow for ward relocation while minimizing disruption.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Highgate West - Can you describe your method for splitting the contract into different sections, and how this benefited the progress of Highgate West?

A

The contract sections were split by each ward/area following discussions with the EA and Employer.

I then sought information required for each sections such as possession date, completion date, liquidated damages rate, rectification period.

Sections allowed the wards not in contractor’s possession to stay live until they were handed over to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

In relation to the Leopold Buildings project, can you detail how you carried out and managed monthly interim valuations?

A

Leopold was under an Intermediate contract, so I would carry out the valuation in line with the due date, with or without contractor application.

I visited site to for a physical verification of work completion as well as reviewing clerk of work reports to determine the accurate value of works completed.

I then discussed my assessment with the contractor to maintain a good working relationship before issuing to the CA for them to issue their Interim Certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Could you elaborate on the process you followed when assessing variation on Leopold, particularly concerning gas pipework rerouting?

A

I studied the contract drawings, identifying the scope of the variation

I communicated with the contractor to get an estimated cost and time impact if applicable before making my assessment.

In the case of the gas pipework rerouting, I analysed the technical necessities and reviewed the contractors costs against benchmark figures that we had on similar projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What did you mean by the Contractor’s requirements under the contract?

A

I meant the works they are required to do under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

How did the contractor’s contract work requirements affect your decision when determining the relevance of the claimed variation costs?

A

I would review the claimed variation and compare the works with the contract works to check if they were a valid variation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Can you share your experience in handling Extensions of Time issued by the Contract Administrator and how did this impact Loss and Expense claims?

A

Extensions of Time changes the way the preliminaries are assessed in interim valuations. Preliminaries should be paused during an EoT period.

I would review the EoT Relevant Event to see if there was an equivalent Relevant Matter to allow the contractor to claim L&E.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How did your understanding of JCT contractual provisions contribute to the final account discussions with the contractor in the Leopold Buildings project?

A

My understanding of the contract final account timelines

I reviewed the EoT’s awarded and which of these enabled the contractor to claim L&E for those periods

I reviewed the instructions issued to determine their value

All of the above enabled me to negotiate and reach a satisfactory final account conclusion for all parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What process and considerations did you have when dealing with matters such as liquidated damages, retention and practical completion?

A

I considered the contract dates, as well as if the EA/CA had issued an extension of time.

I ensured to consider and have a good understanding of the contractual matters including timescales and responsibilities.

I would ensure good communication with all parties involved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

On Leopold, how did you determine if liquidated damages were due and how did you value them?

A

I reviewed the time period between the revised completion date and practical completion and then applied the contract liquidated damages rate to this period. I informed the client of the amount of LD’s that were due to them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What two things need to happen if the employer is to claim Liquidated Damages?
Notice that employer may take liquidated damages Certificate of non completion of the section or works.
26
How did you report the completion of the project works and the final valuation back to the client?
Following receipt of the contractor's final account information, I undertook my own assessment of the final account. Once final account assessment was completed, I prepared a comprehensive final cost report detailing the work done, total costs and my assessment of final account.
27
On Gallery Court, how did you determine if liquidated damages were due and how did you value them?
I reviewed the time period between the revised completion date and practical completion applied the contract liquidated damages rate to this period. Determined that the total was higher than the liquidated damages maximum cap of £150k.
28
You referred to using Pay Less Notices as a form of taking liquidated damages, why can this not be deducted from the valuations?
The JCT D&B contract indicates that LD's can be either paid to the Employer by the client or deducted from sums due to the contractor. (2.29.2) However the interim and final payment clauses do not allow for deduction of the liquidated damages so the deduction would be taken following a notice from the employer that they would be deducting the liquidated damages.
29
You referred to liquidated damages being taken as part of an interim valuation. How can these be taken before the end of the project?
The JCT D&B contract refers to the LD notice being issued between the completion date and the date of practical completion, therefore interim valuations after the completion date could have liquidated damages taken against them, following a notice from the employer that they would be deducting them.
30
What are the timelines for agreeing the final account under JCT Intermediate Contracts?
After PC, contractor has 6 months to provide the necessary documents for adjustment of final account. If not provided in 6 months, CA can give a 1 month notice of requiring contractor documents. If not provided after that 1 month period, the CA or QS can make their assessment using the information available to them. Within 3 months of receipt of contractor's information, the CA or QS must provide their assessment of the L&E and final adjustment.
31
What is the timeline for the final payment under JCT Intermediate Contracts?
CA issues Final Certificate within 28 days of whichever of the following happens last: end of rectification period issue of cert of making good issue of statement of adjustments to contractor Final date for payment is last day of that 28 day period.
32
What are the timelines for agreeing the final account under JCT D&B Contracts?
After PC, contractor has 3 months to provide their Final Statement. If not provided in 3 months, Employer can give a 2 month notice of requiring contractor Final Statement. If not provided after that 2 month period, the Employer can issue their own final statement to the contractor. Employer has till the final due date to dispute anything in the contractor's final statement, or vice versa if the employer issues the final statement.
33
What is the timeline for the final payment under JCT D&B Contracts?
Due date for final payment is one months from whichever of the following happens last: end of rectification period issue of cert of making good issue of final statement to contractor
34
In both the D&B and Intermediate contracts, how long does the Employer/CA have to issue their defects list following the rectification period ending?
14 days
35
What happens if the Employer does not pay the contractor on time.
The contractor may give a 7 day suspension notice as well as an employer default notice. If the reason for default continues for 14 days then the contractor can terminate the contract. (Same for both D&B24 and IC24)
36
For what reasons could an employer terminate the contract?
Contractor suspends works without reasonable cause Contractor fails to proceed regularly or diligently with their contract obligations Contractor refuses to remove non-compliant work Contractor assigns the contract to another party or sub contracts the works or design of the works. Contractor does not comply with CDM regulations
37
For what reasons could a contractor terminate the contract?
(8.9.1) Employer does not pay by final date for payment Employer assigns the contract to another party (7.1) Employer does not comply with CDM regulations Employer interferes with issuing of any certificate due under the contract (intermediate only)
38
What does D&B call amendments to the ER's?
Changes
39
What does Intermediate contract call amendments to the ER's?
Variations
40
What are red flags for contractor insolvency?
slowing down of works supply of materials drying up increasing defective work changes in management additional or inflated payment requests complaints from subcontractors
41
What would you do if a contractor became insolvent?
- Informa all parties involved - Secure the site - Consider stopping pending payments - Take ownership of materials offsite - Schedule all materials - Value completed works and value any defects - Monitor loss & expense incurred by the employer - Terminate the contract - Start the process of appointing a new contractor.
42
What makes a contract binding?
Offer Acceptance Consideration Intent to create legal relations Capacity Legality
43
For interim valuations, what is gross valuation Alternative A?
Stage payments
44
For interim valuations, what is gross valuation Alternative B?
Periodic payments
45
How can loss and expense be ascertained for Contractor's Head Office Overheads?
The value of lost profit/overheads can be determined using the Emden or Hudson formulas. Hudson is based on OH&P percentage included in the tender. Emden uses the actual head office overheads and profit percentage.
46
What are the differences between NEC and JCT
Programme is a contractual document in NEC but not JCT. Project Manager in NEC, Contract Administrator in JCT NEC is in plain English, JCT in complex legal language NEC incorporates time and cost into compensation events, JCT separates them. NEC uses Activity Schedule, JCT uses CSA or BoQ
47
Do all instructions need to be in writing?
In D&B there is an 'Instructions Other than in Writing' Clause (3.7) If Employer gives verbal instruction it is of no immediate affect Contractor has 7 days to confirm the instruction in writing to the employer The employer has 7 days to respond to the confirmation, if they do not then the instruction stands. (Not available in Intermediate contract)
48
How would you deal with damages for late completion when preparing a valuation?
I would not include LD's in the valuation. If a Certificate of non completion and a notice to take damages have both been issued, then no later than 5 before final payment of the valuation, the Employer may issue a notice to request payment or that they will deduct LD's from sums due to the contractor.
49
Are damages subject to VAT?
No they are not. https://www.squirepattonboggs.com/~/media/files/insights/publications/2016/02/liquidated-damages-in-construction-contracts/liquidateddamagesinconstructioncontracts.pdf
50
On a £1m 3-month refurbishment contract, the proven costs to the client were £45K for every extra day the premises were closed to business. How would you advise the Client with regard to damages for late completion?
I would advise the client that they are entitled to include £45k/day in the contract for LDs if it is a genuine pre-estimate of loss, but this is likely to put contractors off from tendering for the project or increase tender sums significantly so a lower sum may be more beneficial to ensure the client receives tender returns that aren't too high.
51
Do the agreed damages amount have to be applied?
No they can be applied at or below the contract LD rate. They cannot be claimed higher.
52
What are some of the differences in approach between NEC and JCT contracts?
JCT (Joint Contracts Tribunal) and NEC (New Engineering Contract) contracts differ in their approach to risk allocation, payment, and dispute resolution.  JCT contracts are more prescriptive, allocating risk to specific parties and often using traditional dispute resolution methods like litigation or arbitration.  In contrast, NEC contracts prioritize collaboration, distribute risk more evenly, and favour early warnings and dispute resolution boards.
53
What are the differences between collateral warranties and third party rights?
Third party rights are due to third parties (funders, purchasers) through the Contracts (Rights of Third Parties) Act 1999. However it is not easy to go through this act so a Collateral Warranty can be used to make things simpler. Creates a contractual link between two parties that wouldn't have had a link otherwise. Examples include: main contractor and funder a sub-contractor and the employer S/C and tenant/purchaser consultant and funder consultant and tenant/purchaser
54
What are collateral warranties and when might you use them?
Creates a contractual link between two parties where there wouldn't have been one otherwise. Ideal for offering cover for defects
55
What was the gallery court project?
It was a cladding project.
56
How are Liquidated Damages calculated on Gallery Court?
They were a genuine pre-estimate of direct loss suffered by the employer in the event of a delay caused by the contractor. Information must be provided by employer, LD's were £2,500. I believe the majority of the pre-estimate of loss suffered by employer was for professional fees.
57
What was adjusted in the final account statement as a result of the information not being provided on Leopold?
After 6 months, they had not provided the information so I gave them 1 months notice to provide their supporting information and they met this deadline.
58
Highgate West - So what challenge did having live wards bring you when you split in the sections up?
Due to being live wards, it was not possible for contractor to do any kind of opening up works in sections before they had possession of each ward/section. There was also additional security in the hospital in general, which required additional training and awareness from the contractor.
59
What was the Liquidated Damages rate at Leopold?
£2,500 per week or part thereof.
60
Arkwright Garages - You produce a modular cost plan and make sure to factor in all the works packages of the building that would not be included in the modular works package. How did you do that?
A quote was acquired from a modular manufacturer. Their quote was reviewed to determine what was not included in it and those works were then added to the cost plan as separate items.
61
Why was £150,000 the maximum cap for this type of project at Gallery Court?
It was a compromise between the client and the contractor, in order to reduce the risk on the contractor and allow them to keep their risk allowance down in the contract sum.
62
What is the traditional contract alternative to ERs?
Drawings and specifications/BoQ/Work Schedule
63
What would you do if a project became delayed.
Request a revised programme. Review cashflow forecast Spread the time related prelims in valuations.