Project Finance Flashcards

(43 cards)

1
Q

What headings / sections would you expect to see in a typical cost report?

A

fixed costs (contract sum)
variable costs (prov sums/quants)
variations (instructions, anticipated instructions, Loss and Expense, risk/contingency)
professional fees
client direct costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a Cashflow?

A

A detailed outline that captures the inflow and outflow of cash associated with a specific project over its life cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Cost Report?

A

A detailed report highlighting the various finances of a project to track overall expenditure against the budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why is it important to report and forecast costs?

A

To keep the client informed of the current financial status of the project and what the potential final account could be.

This may inform decisions later in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you produce a cost assessment for a financial risk?

A

Identify the risk
Evaluate the likelihood of it occurring
Evaluate the potential cost through a combination of research, expert opinion, historical data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What type of risks would you report in a cost report?

A
  • Financial risks - Cost increases
  • Construction risks - unknown ground conditions
  • Regulatory risks - changes to regulations or policies
  • Market risks - Changes in market conditions
  • Design risks - Changes to the design that are not the contractor’s responsibility.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you tell if the financial progression of a project is on track?

A

By review the forecasted project cash flow.

Against the S Curve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If the contractor was behind the cash flow, what would that be an indication of?

A

It would indicate that the works may be behind programme,

or maybe even that the cash flow was unrealistic if works are not behind programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If the contractor was ahead of the cash flow, what would that be an indication of?

A

It would indicate that the works may be ahead of programme,

or maybe even that the cash flow was unrealistic if works are not ahead of programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a S curve?

A

he cumulative costs of a project are plotted against time which, when presented graphically, typically form an ‘S’ shape.

The lower part of the ‘S’ curve indicates the initial phase of the project, where spending is relatively slow because only planning and design are taking place.

The steep middle section of the curve represents the main construction phase where the spending is accelerated.

Finally, the tapering off at the top of the ‘S’ denotes the completion phase, where fine-tuning and finishing touches are being done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Leopold Buildings - How did you produce the cashflows? What information did you need to produce these?

A

I required the following information:
- contractor programme
- contractors costs (s-curve)
- client direct costs
- professional fees
- retention information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Highgate West - You refer to provisional sums, explain the difference between defined and undefined provisional sums.

A

The key difference lies in the level of definition and the allocation of risk.

Defined provisional sums are used for works that are suitably defined (scope, quantity, location) that the contractor can make allowances for programming, planning and pricing prelims.

Undefined provisional sums are used then works are not suitably defined so contractor cannot be expected to make allowance for them in their programming, planning and pricing preliminaries. Contractor may be entitled to an extension of time and/or additional payments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

NRM2 Definition of Defined Prov Sum

A

A sum provided for work that is not completely designed but for which the following information is provided:
• the nature and construction of the work
• a statement of how and where the work is fixed to the building, and what other work should be fixed
• a quantity or quantities that indicate the scope and extent of the work, and
• any specific limitations, etc. identified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

NRM2 Definition of Undefined Prov Sum

A

A sum provided for work that is not completely designed, but for which the information required for a defined provisional sum cannot be provided.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did your cashflow allow for prompt payment by the client?

A

It allowed the client to have the required amounts in place ready to be paid to the contractor and consultants each month.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the timeline for payment in the contract?

A

The final date for payment is 14 days after valuation due date. (both IC 24 and D&B 24)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What happens if the client does not pay the contractor on time?

What is the effect if payment is made late?

A

The contractor may give a 7 day suspension notice as well as an employer default notice.

If the reason for default continues for 14 days then the contractor can terminate the contract.

Simple interest can be charged from final date for payment to actual payment.

(Same for both D&B24 and IC24)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Highgate West - Why was the contractor not able to provide a completely fixed contract sum due to the live wards?

A

The contractor was not able to access all areas of the wards prior to carrying out the works and even where they could, it was not always possible to open up areas to view unknown aspects of the works, M&E for example.

19
Q

Highgate West - What provisional sums were included by the contractor because of the wards being live?

A

There was an issue with gaining access to the mechanical and electrical systems so there were some provisional sums in place for M&E works.

20
Q

Highgate West - What was your advice to the client regarding the liquidated damages rate to be included in the contract?

A
  • I informed the client that the level of liquidated damages must be a genuine pre-estimate of loss to the client in the event of a delay.
  • LD’s are intended to put the client back in the position they would have been had the delay not occurred.
  • It must not be treated as a penalty.
21
Q

Highgate West - What was your advice to the client regarding the total liquidated damages that the client could claim?

A

I reviewed the period between the extended completion date and the expected completion date (or PC if achieved) and multiplied this period by the liquidated damages rate in the contract particulars.

22
Q

Highgate West - What reason did you report to the client for why the contractor was behind the forecasted expenditure?

A

Some of the wards had not been handed over in time, delaying the contractor from starting works on some contract sections.

23
Q

Highgate West - How was the contractor planning to rectify the delay?

A

The employer was not interested in acceleration as there was no guarantee of it working.

Discussions revolved around the contractor’s management and sequencing of the works.

24
Q

Highgate West - What were the timelines for issuing the final account?

A

After PC, contractor has 3 months to provide their Final Statement.

If not provided in 3 months, Employer can give a 2 month notice of requiring contractor Final Statement.

If not provided after that 2 month period, the Employer can issue their own final statement to the contractor.

Employer has till the final due date to dispute anything in the contractor’s final statement, or vice versa if the employer issues the final statement.

25
Highgate West - How did you assess the Loss and Expense due to the contractor?
I asked the contractor to provide evidence of their loss and expense as a result of relevant matters affecting regular progress of the works. I reviewed this information to determine if the costs were as a result of the delay.
26
Highgate West - Why did you advise that the contractor's settlement offer should be accepted?
I had made my own assessment of the final account and the contractors figure was actually marginally lower than my own assessment.
27
Elleray Hall - When advising on alternative specifications , explain how you formulated this advice. EG: How did you come up with the advice? What did you review / study to create your advice?
I reviewed the requirements of the products in terms of cost, durability and aesthetics. I spoke with the architect to ask them for specification suggestions. I then costed the option(s) and presented them to the client and design team for approval.g
28
Elleray Hall - What were the alternative specifications that you advised?
I asked the architect if there was an alternative to the higher specification of paving that had been specified.
29
How did you ensure that the contractor’s additional works were as you term "good value for money"?
I reviewed the additional items against benchmarks and historical data that my company have. I compared my assessment to the contractors cost. I also made sure that the contractor went out to 2 or 3 suppliers to ensure the lowest cost.
30
Did you engage in any third party advice or second opinions at the Elleray Community Hall project with regards to additional scopes of work,
For some of the changes, the flooring for example, I went out to suppliers to acquire quotes/rates for assessment and comparison purposes. I also discussed the changes with other design team members to get their views and opinions.
31
How does a well maintained cashflow forecast benefit the contractor and employer?
Allows contractors and employer to gain an understanding of financial requirements over the duration of the project duration. Also acts as a check against valuations. A positive cashflow will avoid additional finance cost. It is also an early indication of financial difficulties.
32
What is a Scott schedule? When is it used?
Can be used to set out differences in a final account, including difference between contractor and client figures.
33
What are the pros of dayworks?
Contractor reimbursed full costs plus OHP Easier estimation of variations
34
What are the cons of dayworks?
No incentive for contractor to keep time and cost down Contractor paid for all his time and no deduction for mistakes or errors made
35
What would be included in a contractor's Dayworks sheet?
labour plant materials Which unit (hours/quantity?) Used when work cannot be measured
36
What are certain risks that you have included as part of your reporting ?
Financial risks - Cost increases Construction risks - unknown ground conditions Regulatory risks - changes to regulations or policies Market risks - Changes in market conditions Design risks - Changes to the design that are not the contractor's responsibility.
37
What is a final account?
A financial summary that determines the amount owed to the contractor after the project is complete. It accounts for: - initial contract sum - variations - adjustments - loss and expense.
38
For Highgate west, you mentioned provisional sums. Can you explain the risks associated with provisional sums?
The main risk is that costs are not fixed but there can be time risks where the provisional sum is undefined.
39
For the delay experienced in Highgate west, what did you advise to your client?
I suggested to the client that I adjust their expected cashflow to reflect the delay. I also advised the level of liquidated damages the client could potentially claim for periods of delay caused by the contractor.
40
For EH, you mentioned you advised on alternative specs. As a QS, what are the risks of doing so and how can you mitigate any risks associated with this?
The risk is that I could be seen as a designer but I am not qualified or insured as a designer. With all my advice in this regard I will always discuss options the appropriate designer first for them to design something for me to cost.
41
What are CapEx and OpEx?
CapEx (Capital Expenditures) involves significant, long-term investments in tangible assets (like buildings and equipment) that are depreciated over time OpEx (Operational Expenditures) refers to ongoing, recurring costs (like rent and utilities) that are fully deducted in the year they are incurred.
42
What are the risks that you provide cost assessments for in your cost reports?
Costed risk would depend on the project specifics but potential risk cost assessments could relate to loss and expense, anticipated variations, planning costs.
43
What are the risk allowance management methods stated in the RICS Cost Reporting guidance?
In both options below, costs incurred or forecast where no budget provision was made should be deducted from the general risk allowance(contingency). Maintenance Method - Remaining risk allowance is maintained unless expended. Progressive Release Method - Remaining risk allowance is progressively released on an agreed basis, based on either: - programme completion percentage - cost completion percentage