Procurement and Tendering Flashcards
(51 cards)
What is the difference between tendering and procurement?
Procurement is the overall act of obtaining goods and services and includes deciding the strategy for how the goods/services are acquired.
Tendering is part of the procurement strategy. It is the bidding process and how the contractor is appointed.
What are the different types of tender procedures listed in RICS Tendering Strategies guidance note?
Which RIBA Stages for the main two?
Single stage tender - Tender for full works at Stage 4
Two stage tender - When time is constrained. Early contractor involvement. First stage around stage 2 or 3.
Negotiated tender - Single stage with a single contractor. Advantage is speed. No competitive element, which makes it hard to prove value for money in current market.
When would first stage of a two stage tender be tendered?
Some time around stage 2 or 3.
Why did you refer to D&B, traditional, Construction Management and Management contracting as tender procedures?
I meant that I knew the best tender procedures when used for those procurement routes.
What type of projects would suit Construction Management?
complex building
early start on site
greater control over subcontractor selection
experienced client
What type of projects would suit Management Contracting?
complex building
speed is important but client wants less risk
client who wants flexible design but single point of responsibility
Which tender strategy suits Traditional contract and why?
Single stage tender because the design is suitably developed.
Which tender strategy suits D&B contract and why?
Two stage tender so the contractor can positively influence the design and potentially be appointed under PCSA during 2nd stage to carry out design.
Contractor can also get a better understanding of the project before pricing the second stage.
Which tender strategy suits management contracting and construction management and why?
Two stage tender as this enables for a quick start.
There will be a tender to select the management contractor (management fee, prelims and profit) or the construction manager (management fee only).
Then were will be multiple tenders to select the works contractors or the sub-contracts
Succinctly explain the differences between management contracting and construction management.
The management contractor:
- does not directly undertake any of the construction,
- split into packages and carried out by works sub-contractors who are contractually accountable to the management contractor.
Construction manager:
- does not directly undertake any of the construction work
- split into packages and carried out by trade contractors.
- The employer appoints the trade contractors and is directly responsible for them.
- The construction manager manages the works
Explain to me the benefits of two stage tendering from a contractor’s point of view.
Reduces risk as contractor has input in design development
Allows contractor to get to know the project better before providing stage 2 cost.
Enhanced relationship with client and client’s consultants
Reduced tendering costs in the initial stage 1 and increased likelihood of works after stage 2.
What are the processes involved when compiling tender documents?
Request information required (design, JCT document/information, surveys etc)
Produce my documents (prelims and general conditions, pricing document, form of tender, non-collusion certificate)
How would you assess tender returns?
Check that all required information had been provided.
Check tenders for arithmetical errors.
Review cost breakdowns to check for anything not costed.
Raise queries with the tenderers
Make adjustments to the tender figures based on query responses and missing costs
Review non construction items such as overheads and profit, preliminaries, provisional sums.
Produce report based on findings including scoring.
What different types of funding are available for funding a project?
Self financing
Bank loans
Private Finance Initiative, a UK government scheme used to fund public sector projects, like hospitals and schools, by engaging private companies to design, build, finance, and maintain them over a long period.
What does PFI stand for?
Private Finance Initiative
What would be priced in first stage of a 2 stage tender?
Preliminaries
overheads and profit rate
schedule of rates
Cost for PCSA services - Surveys, enabling works etc.
What non cost information would a contractor provide during first stage of a two stage tender?
Provide company information:
* Structure
* Previous projects
* Capabilities
* Strengths etc.
* Financial information
* Social value commitments
* Proposed project team
Are you aware of any updates to the procurement regulations?
Procurement Act 2023
Focused on public procurement
Replaces old procurement rules with a single, simplified framework.
Increases transparency through mandatory public notices and a central digital platform.
Supports SMEs and social enterprises by reducing barriers to entry.
Introduces a debarment list of excluded suppliers.
What were the relevant surveys for the Guy’s plant room tender docs?
3 surveys
- Surveys relating to the plant,
- Roof structure
- R&D survey to check for asbestos.
Guys Hospital - describe to me how you compiled the tender documentation. What information did you include?
I requested the design information from the design team
I produced the contract sum analysis for the tenderers to complete
I also produced the preliminaries and general conditions
I included other documents such as form of tender, declaration of non-collusion, pre construction information and an invitation to tender.
Guy’s Hospital - What was included in the pre-construction health and safety information?
Project Description
Site restrictions and risks
Design and construction hazards
Client’s management of the works requirements
Health and safety file requirements
Guy’s Hospital Plant Room - How did you produce the tenderer long list?
I held meetings and discussions with the client, colleagues and other members of the design team.
We came up with a list of M&E contractors that had previously performed well on projects of a similar size and nature.
Guy’s Hospital Plan Room - What was included in the pre-qualification questionnaire?
Company information
Financial queries (annual turnover for 2-3 years, profit and loss statements, financial stability evidence/checks)
Previous projects of a similar nature
Health and safety record
What is a PQQ?
What is it?
Pre-Qualification Questionnaire
Used in particularly in public sector tenders to assess suitability and eligibility of potential tenderers before they are invited to tender?