A3 Prep Flashcards
(43 cards)
What are two assumptions made in EVA analysis?
1) Valid estimates of % complete.
2) Actual expenditures coincide with work performed (no delayed or advanced payment)
What are the PM’s roles in system fabrication?
Monitoring
Inspecting
Documenting progress
Comparing planned vs actual
Taking corrective actions
Define “monitoring and control”
The process of keeping the project moving as outlined in execution phase.
Define “project control”
Assessing progress against planned objectives / performance and taking corrective action.
Internal control - control imposed by internal project team and stakeholders or party who is constructing / producing the product.
External control - control imposed from client, user or other regulatory party / stakeholder.
What are 5 types of project control?
Scope control
Quality control
Schedule control
Procurement control
Cost control
What is scope creep?
Scope’s tendency to grow over time.
Explain scope control.
Scope tends to increase.
Identify and inspect scope changes.
Determine if changes are really necessary.
Restrain changes as far as possible.
Explain quality control.
Managing work to ensure meet requirements.
Quality management plan.
Explain schedule control.
Keeping project on schedule.
Applying buffers strategically.
Fever chart (how project is doing).
Communicate critical activities.
Explain procurement control.
Control output by controlling suppliers.
Inspection.
According to project procurement plan.
Explain cost control.
Trace variances in expenditures vs budgets and cost plans.
Eliminate unauthorized and inappropriate expenditures.
Minimise cost changes.
What are work packages?
Contracts for specific activity / job with its own requirements:
- work description
- cost
- budget
- schedule
Work authorisation.
- part of project control
- work starts only after formal authorization and is stopped only after review and acceptance of product.
- work authorisation is applied on phase levels and project as a whole.
What are five primary ways for obtaining and conveying project information?
1) Status review meetings.
2) Observations and site meetings.
3) Technology
4) Formal reports and documents.
5) Documentation management.
What are status review meetings for?
List three types of status review meetings.
To assess, communicate progress, and ID deviations and quickly correct them.
1) Informal meetings & reviews.
2) Stand-up meetings
3) Formal meetings
Communication plan includes:
1) schedule for review meetings.
2) milestone meetings
3) important points of contact
WHO
communicate WHAT
WHEN
to WHOM
in WHAT FORMAT
Explain the difference between formal and informal communication?
Formal:
- communication through formal reports and documents
- reports to top management and PMO
- reports to project, program, and functional managers
- reports to customers / users
Informal:
- through the grapevine
- valuable information
What is the PM responsible for in project termination and closeout activities?
A. Planning, scheduling & monitoring closeout activities
- Obtain and approve termination plans
- Prepare and coordinate termination plans and schedules
- Plan for transfer of project team and resources after the project
B. Final closeout activities
- Closeout all work orders and contracts
- Notify all departments of project completion
- Close the project office
- Close the project books
C. Customer acceptance, obligation, payment activities
- Ensure delivery of end and side-items
- Notify customer on fulfilment of contractual obligations
- Ensure all documents are completed
- Transmit formal payment and collect final payments
- Obtain formal acknowledgement of completion
What are two forms of a formal project evaluation?
1) Post-completion project review.
2) Post-installation systems review.
What are direct costs? Give an example.
Costs directly attributable to specific project, product, or service.
- Labour
- Raw materials
- Equipment
- Travel expenses
What are indirect / project overhead costs? Give an example.
Costs that support multiple projects or the overall operation, but are not directly traceable to one specific project.
- Utilities
- Office supplies
- IT support services
What are overhead costs? Give an example.
A subset of indirect costs that covers ongoing operational expenses necessary to run the business but not linked to any one project.
- Rent for office
- Insurance for building
- General maintenance costs
Define “profit and total billing”
The markup applied to cover profit and company overhead.
The Project Management Office (PMO):
Supports and oversees multiple projects
Develops standards, policies, and methodologies
Provides training, resources, and sometimes assigns project managers
Ensures consistency and alignment across all project efforts in an organisation