PJM_A201_Articles_1_7 Flashcards

(26 cards)

1
Q

What document defines the ‘rules’ or ‘terms and conditions’ for owner, architect, and contractor?

A

AIA A201 General Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How is AIA A201 incorporated into agreements?

A

By reference into A101 (owner/contractor) and B101 (owner/architect)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Does anyone sign the A201 document?

A

No, it is incorporated by reference and not signed directly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of A201?

A

To define rights, responsibilities, and relationships of parties in construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What documents are included in ‘contract documents’ per A201?

A

Owner/contractor agreement, A201, supplementary conditions, drawings, specs, addenda, and modifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the difference between ‘the Work’ and ‘the Project’ in A201?

A

‘Work’ is contractor’s scope; ‘Project’ includes all work including that by owner or others

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are specifications in A201?

A

Written requirements for materials, workmanship, performance, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are instruments of service?

A

Architect’s and consultants’ drawings, specs, models, sketches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the contractor’s responsibility regarding site conditions?

A

They must visit the site and be familiar with conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the contractor NOT responsible for?

A

Ensuring documents comply with codes and laws (architect’s responsibility)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Are submittals contract documents?

A

No, they show how contractor will meet requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who prepares the project schedule in A201?

A

The contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can contractor blame missing specification for excluding a required item?

A

No, documents are complementary—required by one means required by all

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who secures building permits under A201?

A

The contractor, unless otherwise noted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who can stop the work according to A201?

A

The owner, not the architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What must the owner provide under A201?

A

Proof of funding, surveys, legal site description

17
Q

What does Article 3.12 protect?

A

Architect, by stating submittal approval doesn’t relieve contractor of responsibility

18
Q

What are three types of changes in the work?

A

Change Order, Construction Change Directive (CCD), Minor Change

19
Q

What is a Change Order?

A

A change agreed upon by owner, architect, and contractor affecting cost/time

20
Q

What is a Construction Change Directive?

A

A change ordered before agreement on time/cost adjustment

21
Q

What is a Minor Change?

A

Change with no impact on cost or time, issued by the architect

22
Q

What is the architect’s responsibility during CA per A201?

A

Administer contract, review payments, site visits, approve submittals

23
Q

What does indemnification in A201 mean?

A

Contractor must protect owner/architect from third-party claims due to their negligence

24
Q

What are subcontractors’ obligations under A201?

A

Bound by terms of main contract, owner/architect can object to them

25
What is the architect not responsible for?
Construction means and methods
26
What benefit does CA phase provide architects?
Opportunity to learn how drawings are built, improve future documents