PJM_Changes_During_Construction Flashcards

(20 cards)

1
Q

What are common reasons for changes during construction?

A

Unforeseen conditions, material/labor availability, client changes, or price fluctuations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What must the architect evaluate when a change occurs during construction?

A

If the change affects price/schedule, its impact on the critical path, and whether it warrants an additional service.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How should schedule changes be evaluated?

A

By analyzing the critical path and float to see if the end date is affected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between a change order and a CCD (Construction Change Directive)?

A

Change orders are used when all parties agree on cost/schedule. CCDs are used when they don’t.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What do minor changes in the work affect?

A

They cannot affect the contract sum or construction schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is a markup calculated?

A

Markup is added to the cost like sales tax. For example: $10,000 x 15% = $1,500; total = $11,500.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is profit margin calculated?

A

Divide cost by (1 - profit %). For $10,000 with 15% margin: $10,000 / 0.85 = $11,765.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What’s the key difference between markup and profit margin?

A

Markup adds a percentage to cost. Profit margin determines total fee to yield a % profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How should substitution change orders be priced?

A

Reflect only the cost difference between the original and substitute item.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who typically proposes pricing for a change order?

A

The contractor, and the architect evaluates fairness based on unit prices or substitutions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What documents authorize changes in construction?

A

AIA A201 Article 7: change orders, construction change directives (CCDs), and minor changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can schedule or cost be affected by a minor change in the work?

A

No, minor changes cannot affect schedule or contract sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What may warrant an architect charging additional service fees during construction?

A

Extended CA duration, multiple project phases, or complex change order evaluation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do project phases affect architect services?

A

Splitting work into phases increases coordination and time, possibly justifying additional fees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What factors might drive a change in construction phasing?

A

Trade coordination, permitting delays, client priorities, or site issues.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How should architects handle added project phases?

A

Submit additional service requests (ASRs) to document extra coordination and time.

17
Q

What should be done if a contractor change order seems overpriced?

A

Evaluate cost breakdown, verify original credits, and ensure only fair increases are included.

18
Q

How can drainage issues affect construction scope?

A

May lead to relocation of elements like wash bays due to jurisdictional water control concerns.

19
Q

What role does the architect play in change order pricing?

A

Review for accuracy, fairness, and compliance with scope; advise client impartially.

20
Q

Why is it important to distinguish markup vs. profit margin on the ARE?

A

Using the wrong formula leads to incorrect calculations and missed points.