PJM_Project_Delivery Flashcards
(23 cards)
What are the owner’s key objectives in project planning?
Budget, schedule, and scope of work.
Which B101 sections cover project milestones and delivery method?
Sections 1.1.4 and 1.1.5.
How does the project delivery method affect the project?
It informs the schedule, milestones, and risk distribution.
What delivery methods are allowed in B101?
Design-bid-build and design-negotiate-build.
What factors affect how the architect delivers a project?
Budget, schedule, scope, software, consultants, and services.
What must the architect submit per B101 Section 3.1.3?
A detailed design schedule for each phase of work.
When should the architect submit their design schedule?
As soon as practicably possible after the agreement date.
What does a detailed project schedule include?
Design milestones, permitting, review periods, and consultant timelines.
Why is a realistic schedule important early on?
To align expectations, secure buy-in, and avoid delays.
How do owner reviews impact the schedule?
They may delay progress if review periods are longer than expected.
Why is construction phasing sometimes required?
To maintain operations during construction (e.g., hospitals).
What does BIM use require in terms of scheduling?
More time upfront for modeling and coordination.
Why must the owner understand BIM scheduling?
Because it front-loads effort, which may delay visible progress early.
What are supplemental services under B101 Article 4?
Programming, site selection, historic preservation, etc.
Where are supplemental services listed in B101?
Section 4.1.1.
Where are additional services after contract execution addressed?
Section 4.2.
Where is compensation for additional services listed?
Section 11.3.
How can additional services be clarified in the contract?
By attaching an exhibit listing possible future services.
Why is consultant coordination important in scheduling?
To ensure all deliverables align with the project timeline.
What does the architect need from owner’s consultants?
Awareness of schedule and coordination of their deliverables.
What should be accounted for when establishing the schedule?
AHJ reviews, consultant timelines, software used, and review time.
Why does scope of work impact schedule?
Because different deliverables require different time investments.
What should the schedule include for phased projects?
Clear construction phases and coordination steps.