PJM_Project_Delivery Flashcards

(23 cards)

1
Q

What are the owner’s key objectives in project planning?

A

Budget, schedule, and scope of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which B101 sections cover project milestones and delivery method?

A

Sections 1.1.4 and 1.1.5.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How does the project delivery method affect the project?

A

It informs the schedule, milestones, and risk distribution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What delivery methods are allowed in B101?

A

Design-bid-build and design-negotiate-build.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What factors affect how the architect delivers a project?

A

Budget, schedule, scope, software, consultants, and services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What must the architect submit per B101 Section 3.1.3?

A

A detailed design schedule for each phase of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When should the architect submit their design schedule?

A

As soon as practicably possible after the agreement date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does a detailed project schedule include?

A

Design milestones, permitting, review periods, and consultant timelines.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why is a realistic schedule important early on?

A

To align expectations, secure buy-in, and avoid delays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do owner reviews impact the schedule?

A

They may delay progress if review periods are longer than expected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why is construction phasing sometimes required?

A

To maintain operations during construction (e.g., hospitals).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does BIM use require in terms of scheduling?

A

More time upfront for modeling and coordination.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why must the owner understand BIM scheduling?

A

Because it front-loads effort, which may delay visible progress early.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are supplemental services under B101 Article 4?

A

Programming, site selection, historic preservation, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Where are supplemental services listed in B101?

A

Section 4.1.1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Where are additional services after contract execution addressed?

17
Q

Where is compensation for additional services listed?

A

Section 11.3.

18
Q

How can additional services be clarified in the contract?

A

By attaching an exhibit listing possible future services.

19
Q

Why is consultant coordination important in scheduling?

A

To ensure all deliverables align with the project timeline.

20
Q

What does the architect need from owner’s consultants?

A

Awareness of schedule and coordination of their deliverables.

21
Q

What should be accounted for when establishing the schedule?

A

AHJ reviews, consultant timelines, software used, and review time.

22
Q

Why does scope of work impact schedule?

A

Because different deliverables require different time investments.

23
Q

What should the schedule include for phased projects?

A

Clear construction phases and coordination steps.