PJM_Additional_Services_Scope_Change Flashcards

(15 cards)

1
Q

What defines the architect’s scope of work in a project?

A

The B101 Owner/Architect Agreement defines the architect’s basic and supplemental services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are supplemental services under B101?

A

Services agreed upon before the project starts and listed in the agreement, such as BIM management, programming, or commissioning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are additional services under B101?

A

Services that arise after the agreement is signed and change the architect’s original scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When does a change in the architect’s responsibilities qualify as an additional service?

A

When the client requests new tasks, such as presentations or new scope items not in the original agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Does a change in the owner’s budget during design trigger an additional service?

A

Yes, redesigning to meet a new budget is considered an additional service.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is redesigning due to high contractor bids the architect’s responsibility without extra compensation?

A

If the bids exceed budget due to architect error or poor estimating, the redesign must be done at no additional cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What exception allows the architect to be compensated for redesign if bids come in over budget?

A

If unexpected market conditions (e.g., inflation) caused the overage, per B101 Article 6.7.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is life cycle cost analysis (LCCA)?

A

A method for evaluating the total cost of a building component over time, including initial, operational, maintenance, and disposal costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How should an architect respond to owner requests outside the original agreement?

A

Notify the owner, document it as an additional service, and ensure proper compensation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What triggers an additional service when initial information changes?

A

Changes in size, program, schedule, or budget that affect the architect’s scope of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What’s a good strategy for managing additional services?

A

Understand the scope in the B101 agreement and proactively identify changes early to ensure compensation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Give an example of value engineering as an additional service.

A

Reducing building footprint or finish quality to meet revised budget during design phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How should alternates be handled in response to budget issues?

A

Include alternate options in documents to help the owner make informed decisions if bids exceed the budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What happens if additional services are performed without agreement?

A

The architect may risk not being compensated; always seek approval before proceeding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How is reducing floor-to-floor height an example of value engineering?

A

It maintains usable space and rentability while lowering construction cost to meet the owner’s budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly