PJM_A201_Articles_8_15 Flashcards

(22 cards)

1
Q

What does Article 8 of A201 define?

A

It defines contract time and conditions for extending the construction schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Under what circumstances can the contractor extend the schedule?

A

Unforeseeable weather, labor disputes, fire, delays caused by the owner or architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is required for a contractor to request a time extension?

A

Submit a change order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What triggers the payment process in Article 9?

A

Contractor submits an Application for Payment to the architect at least 10 days before the payment date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What can the architect do upon receiving a payment application?

A

Certify full payment, certify a partial amount, or withhold payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is substantial completion?

A

When the work is sufficiently complete for the owner to occupy and use the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the steps to certify substantial completion?

A

Contractor submits punch list, architect inspects, architect issues Certificate of Substantial Completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does Article 10 cover?

A

Contractor’s responsibility for site safety and handling hazardous materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who is responsible for hazardous materials?

A

The owner, unless the contractor fails to notify about unknown hazards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is required insurance for the contractor?

A

Commercial general liability, workers’ compensation, and any specialty insurances required in Exhibit A of A101.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who must be named as additional insureds on contractor’s CGL policy?

A

Owner, architect, and architect’s consultants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a waiver of subrogation?

A

Agreement that parties won’t sue each other for damages covered by property insurance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does Article 12 address?

A

Uncovering and correction of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When can the contractor get additional compensation for uncovering work?

A

If the architect did not clearly request observation before the work was covered and it complies with contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How long is the contractor required to correct work?

A

During construction and up to one year after Substantial Completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Article 13 about?

A

Miscellaneous provisions including tests and inspections.

17
Q

What scenarios allow the contractor to terminate the contract?

A

Court/government stop orders, nonpayment, or owner’s failure to meet obligations for 60+ days.

18
Q

What rights does the owner have for termination?

A

Suspend or terminate for convenience or for cause.

19
Q

What happens if the owner terminates for convenience?

A

Contractor is paid for completed work, termination costs, and fee stated in A101.

20
Q

What happens if the contractor is terminated for cause?

A

They receive no termination fee.

21
Q

What is the dispute resolution process in Article 15?

A

Initial Decision Maker → Mediation → Binding Dispute Resolution (arbitration/litigation).

22
Q

What is the deadline to file claims under A201?

A

Within 21 days of the event and no more than 10 years after Substantial Completion.