PJM_A101_Key_Articles Flashcards

(13 cards)

1
Q

What is the A101 contract used for?

A

Construction contracts with a stipulated sum, typically for large or complex projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What documents are included in Article 1 of A101?

A

The agreement itself, architect’s drawings, specifications, addenda, A201 general conditions, Exhibit A (insurance/bonds), and E203 (BIM exhibit).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does Article 2 of A101 state?

A

The contractor shall fully execute the work described in the contract documents, unless noted as the responsibility of others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does Article 3 of A101 specify?

A

The commencement date, substantial completion date, and that the schedule can only be changed by change order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the three ways to define the date of commencement under A101?

A

Date of agreement, date in notice to proceed, or a specific date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the definition of substantial completion in A101?

A

When the work is sufficiently complete for the owner to occupy or use for its intended purpose.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why is the substantial completion date important?

A

It starts project warranties and affects the statute of repose.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is specified in Article 4 of A101?

A

The stipulated contract sum, selected alternates, allowances, unit prices, and liquidated damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are alternates in Article 4?

A

Changes to the scope that may be accepted at the time of or after contract execution with specific prices.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are allowances in Article 4?

A

Estimated costs for undefined materials or scopes at the time of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are unit prices in Article 4?

A

Prices per unit of work for scopes with uncertain quantities, typically including all labor, materials, and overhead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are liquidated damages in A101?

A

Optional penalties paid by the contractor for not achieving substantial completion on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What must be done to incorporate all construction documents into the A101?

A

List them explicitly in Article 9 or in an attached exhibit to make them part of the agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly