PJM_Constructor_Communication Flashcards

(22 cards)

1
Q

What is the architect’s key responsibility during construction?

A

Ensure the constructor understands the design intent and administer the construction contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What document outlines the architect’s CA responsibilities?

A

AIA B101, Article 3.6.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Is the architect responsible for means and methods of construction?

A

No, that’s the constructor’s responsibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why is it risky for architects to comment on means and methods?

A

It increases liability and may not be covered by professional liability insurance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How should informal on-site discussions be followed up?

A

With written documentation and clarifying sketches if needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What should be done after each site visit?

A

Issue a field observation report with date, number, and distribute to relevant parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an RFI?

A

Request for Information—used by the constructor to ask for clarifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Where should the RFI process be outlined?

A

In the procurement documents (e.g., project manual, drawings, addenda).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What should the architect do before responding to an RFI?

A

Thoroughly review it and consult with consultants if needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who communicates with consultants regarding RFIs?

A

The architect—not the owner or contractor directly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What happens if the architect delays RFI responses?

A

The constructor may claim project delay due to the architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a submittal?

A

Shop drawings, product data, or samples submitted by the constructor or subs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the purpose of submittals?

A

To show that selected materials align with design intent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Should the architect approve submittals related to means and methods?

A

No—those are outside the architect’s scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a submittal schedule?

A

A list prepared by the constructor outlining review timelines aligned with construction schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are OAC meetings?

A

Owner-Architect-Constructor meetings held regularly to discuss project issues.

17
Q

Who typically leads OAC meetings?

A

The constructor, since they manage the construction schedule.

18
Q

What should be produced during OAC meetings?

A

Meeting minutes that document topics and decisions.

19
Q

What should the architect do if someone else prepares OAC meeting minutes?

A

Review, correct, and clarify them in writing before the next meeting.

20
Q

Why is regular documentation during CA important?

A

It helps minimize risk and ensures accountability.

21
Q

What kinds of communication are considered formal during CA?

A

RFIs, submittals, field reports, and OAC meeting minutes.

22
Q

What is the architect’s role in certifying payment?

A

Evaluate work and approve applications for payment based on progress and quality.