Regulatory_Review_and_AHJ Flashcards

(20 cards)

1
Q

What is the architect’s responsibility according to B101, Article 3.1.6?

A

Assist the owner with filing documents required by the AHJ for project review and approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does AHJ stand for?

A

Authority Having Jurisdiction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why is it important to schedule an initial meeting with the AHJ?

A

To introduce the project and confirm specific submission, review, and approval requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are common documents required in a permit submission to the AHJ?

A

Construction drawings, zoning and code compliance sheets, energy code compliance data, surveys, and AHJ-specific forms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why should you understand AHJ review timelines early in a project?

A

To incorporate review time and possible revisions into the project schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of zoning and code compliance sheets?

A

To summarize applicable requirements and demonstrate how the project complies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why is it risky to delay checking submission requirements until the last minute?

A

Some jurisdictions require specific formats or physical stamps, which can delay submission if unprepared.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What should the architect do before submitting for permit?

A

Follow the firm’s QA/QC procedures to ensure quality and completeness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the contractor’s responsibility after CDs are approved?

A

Apply for the building permit and provide additional documentation like licensure and safety plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What happens if the AHJ requests revisions to a submission?

A

The architect must revise the documents to address the issues and resubmit for approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who is responsible for resolving AHJ comments in a revised submission?

A

The architect, by adjusting the design to meet requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What should a project manager do when AHJ objections are received?

A

Review all objections before assigning resolution tasks to staff.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What’s a common cause of project delays during permit review?

A

Incomplete or non-compliant documentation submitted to the AHJ.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When should a contractor pull the building permit?

A

After the CDs are approved and required documentation is prepared.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the importance of the Certificate of Occupancy (CO)?

A

It allows the owner to officially occupy the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why should the CO be obtained before issuing the Certificate of Substantial Completion?

A

Because the owner cannot occupy the building without the CO.

17
Q

What types of inspections occur during construction for code compliance?

A

Rebar before concrete, and MEP components before they are enclosed.

18
Q

What is the architect’s role during construction regarding inspections?

A

Be familiar with required inspections and ensure the contractor includes them in the schedule.

19
Q

How does a zoning plan reviewer sometimes require dimension info?

A

To be clearly shown on architectural plans even if included in the site survey.

20
Q

What is a common AHJ requirement that can be missed late in the process?

A

Printed, stamped drawing sets or physical document delivery.