PJM_Contract_Documents_Usage Flashcards

(15 cards)

1
Q

What are contract documents in the context of construction?

A

They include the owner-contractor agreement (e.g., A101), general conditions (e.g., A201), supplemental conditions, drawings, specifications, contract forms, and pre-contract addenda.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What role do construction documents (CDs) play during bidding and contract administration?

A

They are the basis for bids, contractor evaluation, RFIs, submittals, and project closeout activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the difference between contract documents and construction documents?

A

Construction documents refer to drawings and specifications. Contract documents include those plus agreements, general and supplemental conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What should you look for when reviewing bids?

A

Check for completeness, correct format, and alignment with bidding requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Are bidding requirements part of the contract documents?

A

No. Since bidding ends when the contract is signed, they are not incorporated into the construction contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is an RFI (Request for Information)?

A

A formal contractor request to clarify missing or unclear information in the CDs. It is not for redesign.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What should an architect do when responding to an RFI?

A

Review the CDs, locate relevant info, and respond professionally. Provide supplemental info if needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When does an RFI become an additional service?

A

When the requested info is already in the CDs and the architect is asked to provide it again.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are submittals?

A

Documentation from contractors showing products/assemblies to be installed, to confirm compliance with design intent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the contractor’s role in submittals?

A

They must review and approve submittals before sending them to the architect, per A201.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What should the architect confirm in a submittal review?

A

Ensure it’s required, does not address means/methods, and complies with CDs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What should not be reviewed by the architect in submittals?

A

Contractor means and methods (e.g., shoring), which should be marked as ‘not reviewed’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does CD clarity impact RFIs and submittals?

A

Clear CDs reduce unnecessary RFIs and increase quality submittals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the architect’s responsibility at project closeout?

A

Determine compliance with CDs, issue certificates of substantial and final completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What closeout information is found in contract documents?

A

Turnover procedures, warranties, final payment process, and punch list requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly