PJM_Delivery_Methods Flashcards

(18 cards)

1
Q

What is a project delivery method?

A

A strategy that defines the organization, contractual relationships, and responsibilities of key players for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What factors should be considered when advising on a delivery method?

A

Client goals, experience, need for control, pricing strategy, and preferred interaction with constructor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the most common project delivery methods?

A

Design-Bid-Build (DBB), Design-Build (DB), Construction Management (CMa, CMc), and Integrated Project Delivery (IPD).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What contracts are typically used in Design-Bid-Build?

A

AIA B101 (Owner-Architect), AIA A101 (Owner-Contractor), AIA A201 (General Conditions).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Design-Negotiate-Build?

A

A variation of DBB where the owner negotiates pricing with selected contractors instead of competitive bidding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the role of a Construction Manager as Advisor (CMa)?

A

Provides constructability and cost input; does not build the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the contracts used with CMa?

A

B132 (Owner-Architect), C132 (Owner-CMa), A132 (Owner-Contractor).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is CMc (Construction Manager as Constructor)?

A

CM provides pre-construction advice and later constructs the project, often under a GMP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the risks of fast tracking a project?

A

Uncoordinated documents, scope changes, errors in early bid packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the main feature of Design-Build?

A

Single contract between owner and design-builder.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What contracts are used in contractor-led Design-Build?

A

A141 (Owner-Design-Builder), B143 (Design-Builder-Architect).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who is the architect’s client in Design-Build?

A

The Design-Builder.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a potential downside for the owner in Design-Build?

A

Reduced quality oversight and loss of an independent architect’s advocacy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Bridged Design-Build?

A

Design architect develops design; then a design-build entity executes it with the original architect as owner advisor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What defines Integrated Project Delivery (IPD)?

A

Early involvement, shared risk and reward, collaborative decision-making.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What AIA contracts support IPD?

A

A195 (Owner-Contractor), B195 (Owner-Architect), A295 (General Conditions).

17
Q

Why is selecting a delivery method an early priority?

A

It defines roles, relationships, staffing, planning, and contract documents.

18
Q

What should be considered when selecting a delivery method?

A

Project scope, budget, schedule, owner experience, quality expectations, and team dynamics.