MAIN ELECTRICAL DISTRIBUTION Flashcards

1
Q

What are the minimum conditions for criticality?

A

2 EDGs with 25K gallons, 1 6900V bus, 2 230kV lines, 1 230kV bus, and batteries with 2 chargers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the minimum grid voltage before auxiliary transformers are declared INOPERABLE?

A

223kV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the LCO for 1 auxiliary transformer INOP?

A

30-day LCO with EDG running.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the LCO for 1 EDG INOP?

A

7-day LCO with redundant EDG operable and tested within 24 hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the LCO for 2 EDGs INOP or 1 EDG and 1 auxiliary transformer INOP?

A

12 hours to Hot Shutdown (HSD).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What action is required if only 1 230kV line is available or there is a load rejection?

A

Start and run a diesel generator continuously.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens if grid voltage drops below 223kV?

A

Both auxiliary transformers are declared INOPERABLE, and you enter 3.0.1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the function of the Rapid Pressure Relief Device (MPT)?

A

It uses 2 of 2 logic to trip the main generator breaker and exciter breaker.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the precaution for aligning 4kV ES buses to a single transformer?

A

Do NOT align them due to the risk of separation from the grid during ES block loading.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the limitation for the 1N high side breaker change?

A

Limited to <70 Amps as measured on the high side; otherwise, the 1J cross-tie breaker will trip on overload.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What happens to RCP motor currents on lowering grid voltage?

A

RCP motor currents rise towards the trip setpoint, and the compensatory action is to raise MVAR output.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where are DCA and DCB located?

A

On the West Wall of the Substation Building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the procedure for opening the 1Y 480V disconnect switch under load?

A

It must be opened procedurally by first opening the 480V feeder to minimize arc damage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the function of the Bell Alarm Switch?

A

It indicates overcurrent and requires the manual trip button to reset

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What action is required if 1091 and 1092 are OOS with a fault on the 4 Bus?

A

The reactor must be in Hot Shutdown (HSD), and criticality cannot be achieved until a second 230kV line is available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly