UPS DIESEL Flashcards

(15 cards)

1
Q

What does the UPS Diesel provide power to?

A

Vital security loads such as lighting, electronic surveillance, access controls, communications, and processing equipment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How long is power temporarily lost to non-vital security loads during UPS Diesel startup?

A

Approximately 3 seconds until EG-Y-2 is up to voltage and frequency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the trip conditions for EG-Y-2 UPS Diesel?

A

Low oil pressure (20#), high water temperature (210°F), and overspeed (2100 rpm).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the normal shutdown procedure for the UPS Diesel?

A

A 5-minute unloaded run to cool down.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What happens during an emergency shutdown of the UPS Diesel?

A

The UPS Diesel stops immediately with no cooldown, bypassing the cooldown using a locally mounted emergency stop button.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How quickly does the UPS Diesel provide power after a loss of normal power?

A

Within 3 seconds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How long is the time delay for the UPS Diesel to transfer back to 1E 480V on restoration of normal power?

A

30 seconds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the minimum fuel level required in the UPS Diesel Fuel Tank DF-T-13 to meet the mission time?

A

275 gallons to meet the 24-hour mission time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Where is the Auto Transfer Switch (SED-SEC-9) located?

A

On the 2nd Floor Mezzanine above the machine shop.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What triggers the UPS Diesel Generator to start?

A

Loss of power to the 1E 480V RB H&V Bus.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What happens after the 1E 480V RB H&V Bus is re-energized?

A

The Auto Transfer Switch cancels the start signal and auto transfers back to normal AC after a delay of 0.5 to 30 minutes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What type of switch is the ASCO Auto Transfer Switch (SED-SEC-9)?

A

It is a NORMAL SEEKING switch.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does the UPS Inverter do?

A

It provides uninterruptable power from the UPS battery bank to SED-SEC-3 (vital security loads) until EG-Y-2 is up to voltage and frequency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What precaution must be taken before operating the Auto Transfer Switch (SED-SEC-9) manually?

A

Ensure that both normal and emergency power supplies are de-energized.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the largest load on EG-Y-2?

A

Perimeter lighting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly